1539-1541 E 22ND ST 90011
Certificate Information: 1539-1541 E 22ND ST 90011
- Application / Permit
- 24010-20000-05379
- Plan Check / Job No.
- B24VN27206
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan. NEW 94' X 25' TWO STORY DUPLEX WITH ATTACHED GARAGE. EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/18/2025
- Issuing Office
- Current Status
- CofO Issued on 11/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | SELLA BENYAMIN |
| Corrections Issued | 1/14/2025 | SELLA BENYAMIN |
| Quality Review Completed | 1/15/2025 | STEVEN KIM |
| Plan Check Approved | 3/7/2025 | SELLA BENYAMIN |
| Issued | 3/18/2025 | APPLICANT |
| CofO in Progress | 11/14/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
| CofO Issued | 11/16/2025 | DEROLD HAUFF |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 1/28/2025 | YASMINE BASHIRI |
| Address approval | Cleared | 1/30/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/30/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/3/2025 | JERRY KAO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | WALLIE JONG |
| Sewer availability | Cleared | 2/21/2025 | WALLIE JONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 4/10/2025 | Conditional Approval | ALEX COLIN |
| Sewer | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 4/24/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 4/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 5/21/2025 | Conditional Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/6/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/6/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 6/10/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 6/10/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 6/10/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 6/12/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/23/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 6/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/9/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 10/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/14/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |