1205 W 29TH ST 90007

Certificate Information: 1205 W 29TH ST 90007

Application / Permit
24010-20000-05327
Plan Check / Job No.
B24VN27005
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN*23' X 33'-6" TWO STORY ACCESSORY DWELLING UNIT WITH ATTACHED 15'-6" X 19' GARAGE WITH LAUNDRY INSIDE
Permit Issued
Issued on 3/11/2025
Issuing Office
Current Status
CofO in Progress on 9/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 SELLA BENYAMIN
Corrections Issued 1/9/2025 SELLA BENYAMIN
Quality Review Completed 1/9/2025 STEVEN KIM
Plan Check Approved 3/11/2025 SELLA BENYAMIN
Issued 3/11/2025 APPLICANT
CofO in Progress 9/9/2025 ARTHUR NEGRETE
No Progress 9/11/2025 DEROLD HAUFF
CofO in Progress 9/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/16/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/17/2025 CELINA MORENO
Sewer availability Cleared 1/17/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 1/23/2025 CELINA MORENO
HPOZ Cleared 1/30/2025 ERIK VAN BREENE
Miscellaneous Cleared 1/30/2025 ERIK VAN BREENE
ZI Cleared 1/30/2025 ERIK VAN BREENE

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Yiu,, Siu; Lic. No.: S5801 PO BOX 1752      TEMPLE CITY, CA 91780

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 4/2/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 4/2/2025 Partial Approval WILLIAM SIERRA
METHANE-Barrier 4/3/2025 No Access for Inspection WILLIAM SIERRA
Underground Mechanical 4/3/2025 No Access for Inspection WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 4/8/2025 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 4/8/2025 Corrections Issued WILLIAM SIERRA
METHANE-Barrier 4/8/2025 Not Ready for Inspection WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 4/9/2025 Approved WILLIAM SIERRA
METHANE-Barrier 4/9/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Approved WILLIAM SIERRA
HVAC-Rough 5/29/2025 Corrections Issued WILLIAM SIERRA
METHANE-Rough 5/29/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 5/29/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 5/30/2025 Approved WILLIAM SIERRA
HVAC-Rough 5/30/2025 Not Ready for Inspection WILLIAM SIERRA
Wood Frame 5/30/2025 Not Ready for Inspection WILLIAM SIERRA
BUILDING-Rough-Frame 6/3/2025 Conditional Approval WILLIAM SIERRA
HVAC-Rough 6/3/2025 Conditional Approval WILLIAM SIERRA
METHANE-Rough 6/3/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 6/3/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 6/3/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 6/4/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 6/4/2025 Approved WILLIAM SIERRA
HVAC-Rough 6/4/2025 Conditional Approval WILLIAM SIERRA
METHANE-Rough 6/4/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 6/4/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 6/4/2025 Approved WILLIAM SIERRA
Insulation 6/9/2025 Not Ready for Inspection ALEX COLIN
Insulation 6/10/2025 Approved WILLIAM SIERRA
Drywall Nailing 6/13/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 6/16/2025 Approved WILLIAM SIERRA
Sewer 8/1/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 8/8/2025 Approved OSVALDO PARAMO
Final 8/8/2025 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 8/8/2025 Approved OSVALDO PARAMO
HVAC-Final 8/8/2025 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 8/8/2025 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 8/8/2025 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 8/8/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 8/12/2025 Approved WILLIAM SIERRA
HVAC-Final 8/12/2025 Approved WILLIAM SIERRA
PLUMBING-Final 8/12/2025 Approved WILLIAM SIERRA
Final 8/13/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 8/13/2025 Corrections Issued WILLIAM SIERRA
Smoke Detectors 8/13/2025 Approved WILLIAM SIERRA
Final 9/8/2025 OK to Issue CofO ARTHUR NEGRETE
Service/Power Release 9/8/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 2/2/2026 Corrections Issued BRENDAN MORELLI