11554 W ARMINTA ST 91605
Certificate Information: 11554 W ARMINTA ST 91605
- Application / Permit
- 24010-20000-05303
- Plan Check / Job No.
- B24VN26891
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New 2-story detached ADU 710 SF LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | VARAND SARKISIAN |
| Corrections Issued | 1/6/2025 | VARAND SARKISIAN |
| Quality Review Completed | 1/7/2025 | GARO TELMI |
| Plan Check Approved | 1/22/2025 | VARAND SARKISIAN |
| Issued | 1/29/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | MATTHEW NELSON |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
| CofO Issued | 12/12/2025 | RUBEN SALAS |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2025 | KEVIN CHUNG |
| Clean Up Green Up | Cleared | 1/8/2025 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 1/8/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 1/8/2025 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | KEVIN CHUNG |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/28/2025 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/2/2025 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 7/2/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 7/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 7/2/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Wood Construction | 7/8/2025 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/14/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 7/14/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/14/2025 | Corrections Issued | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/14/2025 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/17/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 7/17/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/17/2025 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 7/17/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 7/17/2025 | Partial Approval | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/17/2025 | Partial Inspection | MATTHEW NELSON |
| Insulation | 7/23/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/23/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 7/23/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 7/29/2025 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/24/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Final | 10/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 10/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 10/24/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/24/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 10/24/2025 | Partial Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Final | 11/10/2025 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 11/10/2025 | Approved | MATTHEW NELSON |