10349 N GOTHIC AVE 91344

Certificate Information: 10349 N GOTHIC AVE 91344

Application / Permit
24010-20000-05284
Plan Check / Job No.
B24VN26779
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ALL ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 JEROME MAGAT PALMA
Corrections Issued 1/6/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/8/2025 APPLICANT
Issued 3/18/2025 APPLICANT
CofO in Progress 11/19/2025 CHRISTOPHER ROJAS
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/22/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/22/2025 CARLOS AGUILERA
Watercourse Cleared 1/23/2025 CARLOS AGUILERA
Construction near power lines Cleared 3/3/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 3/6/2025 CARLOS AGUILERA
Sewer availability Cleared 3/6/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/19/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/22/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/26/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/2/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/8/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/8/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 7/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 7/8/2025 Approved CHRISTOPHER ROJAS
Wood Frame 7/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/28/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 7/28/2025 Approved CHRISTOPHER ROJAS
Insulation 8/8/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 8/8/2025 Approved CHRISTOPHER ROJAS
Insulation 8/11/2025 Approved CHRISTOPHER ROJAS
Sewer 8/11/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/21/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/21/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 9/26/2025 Corrections Issued CHRISTOPHER ROJAS
Final 9/26/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 9/26/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 9/26/2025 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 9/26/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 9/26/2025 Approved CHRISTOPHER ROJAS
Final 10/20/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/20/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 10/20/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 10/24/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 10/24/2025 Corrections Issued CHRISTOPHER ROJAS
Final 11/19/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 11/19/2025 Approved CHRISTOPHER ROJAS