4165-4167 N NAGLE AVE 91423
Certificate Information: 4165-4167 N NAGLE AVE 91423
- Application / Permit
- 24010-20000-05278
- Plan Check / Job No.
- B24VN26746
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE SFD EXCEPT 2.25LF INTERIOR WALL W/ FOOTING & ADD (N) 2-STORY SFD W/ ATTACHED 2-CAR GARAGE & ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(e) [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/29/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/2/2025 | JASON HEALEY |
| Building Plans Picked Up | 1/3/2025 | APPLICANT |
| Applicant returned to address corrections | 2/18/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/25/2025 | NILOOFAR MEHRAIN |
| Issued | 2/25/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | CHRISTOPHE COCHRAN |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/10/2025 | RYAN CASTRO |
| Low Impact Development (LID) | Cleared | 1/15/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | RYAN CASTRO |
| Permit | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 1/31/2025 | MIGUEL ORNELAS |
| GPI Written Notices | Cleared | 2/18/2025 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 2/18/2025 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/2/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/11/2025 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 4/14/2025 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 4/15/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 4/22/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/25/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 6/25/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/30/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/1/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/1/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/9/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/18/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 7/22/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 7/25/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/25/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 7/30/2025 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 7/30/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/29/2026 | Corrections Issued | MISAEL ESPARZA |
| Final | 2/5/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Gas Test | 2/5/2026 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 2/5/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/5/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/10/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/10/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/27/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |