8503 N LOUISE AVE 91325

Certificate Information: 8503 N LOUISE AVE 91325

Application / Permit
24010-20000-05271
Plan Check / Job No.
B24VN26727
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-4" X 27'-2" IRREGULAR SHAPED ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 5/2/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 SELLA BENYAMIN
Corrections Issued 1/14/2025 SELLA BENYAMIN
Quality Review Completed 1/16/2025 STEVEN KIM
Building Plans Picked Up 1/16/2025 APPLICANT
Plan Check Approved 4/29/2025 SELLA BENYAMIN
Issued 5/2/2025 APPLICANT
CofO in Progress 10/21/2025 NICHOLAS TROWBRIDGE
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/31/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/4/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/4/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 2/18/2025 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2025 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 5/27/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/8/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 7/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/30/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 7/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/30/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 8/1/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 8/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 8/1/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 8/1/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/5/2025 Partial Approval NICHOLAS TROWBRIDGE
Underground Mechanical 8/5/2025 Approved NICHOLAS TROWBRIDGE
Insulation 8/12/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 8/12/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 8/22/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/22/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/14/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/14/2025 Corrections Issued CHRISTOPHER ROJAS
Final 10/14/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/14/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 10/14/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/14/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 10/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 10/14/2025 Approved CHRISTOPHER ROJAS
Final 10/20/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Service/Power Release 10/20/2025 Approved NICHOLAS TROWBRIDGE