3873 S HARVARD BLVD 90062

Certificate Information: 3873 S HARVARD BLVD 90062

Application / Permit
24010-20000-05269
Plan Check / Job No.
B24VN26700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 26'-9" X 18' DETACHED TWO STORY SINGLE FAMILY DWELLING PER SB9; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 SELLA BENYAMIN
Corrections Issued 1/16/2025 SELLA BENYAMIN
Quality Review Completed 1/22/2025 STEVEN KIM
Building Plans Picked Up 1/27/2025 APPLICANT
Plan Check Approved 3/27/2025 SELLA BENYAMIN
Issued 4/15/2025 APPLICANT
CofO in Progress 3/29/2026 SABAS ALONSO
Permit Finaled 3/30/2026 DEROLD HAUFF
CofO Issued 3/30/2026 DEROLD HAUFF
Permit Finaled 3/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/25/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/31/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 2/11/2025 ROSALINDA MEZA
Sewer availability Cleared 2/20/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/11/2025 JUSTIN BICOL
ZI Cleared 3/14/2025 MANERI ROMAN
Hydrant and Access approval Cleared 3/18/2025 FRANK GOMEZ
Construction near power lines Cleared 3/21/2025 RIDWAN HARDY
Miscellaneous Cleared 3/27/2025 ROSALINDA MEZA

Contact Information

Contractor Beneflipper Construction Corp; Lic. No.: 1071558-B 1715 E 1ST      LONG BEACH, CA 90802
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2025 Partial Approval SABAS ALONSO
Sewer 4/16/2025 Approved SABAS ALONSO
Underground Mechanical 4/16/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/25/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 7/24/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 7/24/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/24/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/13/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 8/13/2025 Approved SABAS ALONSO
Green Building Rough 8/13/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 8/13/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 8/13/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/15/2025 Approved SABAS ALONSO
HVAC-Rough 8/15/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 8/15/2025 Approved SABAS ALONSO
Insulation 8/29/2025 Corrections Issued JOSH MEISTER
Insulation 9/23/2025 Approved ANTHONY RAMOS
Drywall Nailing 10/6/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/6/2025 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 10/15/2025 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 11/7/2025 Approved ANTHONY RAMOS
Shower Pan 11/7/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 12/18/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 12/18/2025 Approved SABAS ALONSO
Final 12/30/2025 Not Ready for Inspection SABAS ALONSO
Green Building Final 12/30/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready SABAS ALONSO
Service/Power Release 12/30/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 12/30/2025 Approved SABAS ALONSO
Final 2/18/2026 Corrections Issued SABAS ALONSO
Green Building Final 2/18/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 2/18/2026 Not Ready for Inspection SABAS ALONSO
Final 3/3/2026 Corrections Issued SABAS ALONSO
Service/Power Release 3/3/2026 Not Ready for Inspection SABAS ALONSO
Final 3/25/2026 Not Ready for Inspection SABAS ALONSO
Service/Power Release 3/25/2026 Corrections Issued SABAS ALONSO
Final 3/27/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 3/27/2026 Approved SABAS ALONSO