8831 N ODESSA AVE 91343
Certificate Information: 8831 N ODESSA AVE 91343
- Application / Permit
- 24010-20000-05189
- Plan Check / Job No.
- B24VN26181
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New 1 story detached ADU per state law
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | ADAM HEGAZI |
| Corrections Issued | 1/7/2025 | ADAM HEGAZI |
| Plan Check Approved | 1/29/2025 | ADAM HEGAZI |
| Issued | 1/30/2025 | APPLICANT |
| CofO in Progress | 10/2/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 10/7/2025 | RUBEN SALAS |
| Permit Finaled | 10/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/8/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/8/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | LEE GUILBEAUX |
| Hold | Cleared | 1/28/2025 | TERESA RIVAS |
| Sewer availability | Cleared | 1/28/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/3/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Special/Order Compliance | 2/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/3/2025 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/6/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 4/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/15/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 4/15/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/23/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/23/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/30/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/30/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/30/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 5/16/2025 | Partial Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 5/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 5/27/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 6/2/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 6/13/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 6/25/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 6/30/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 7/7/2025 | Approved | MICHAEL CORTEZ |
| Final | 8/25/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 8/25/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 8/25/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 8/25/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Special/Order Compliance | 8/25/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Pre-Inspection | 9/23/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 10/2/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 10/2/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/2/2025 | Approved | GAREN HAYRAPETYAN |