8130 N SYLMAR AVE 91402
Certificate Information: 8130 N SYLMAR AVE 91402
- Application / Permit
- 24010-20000-05172
- Plan Check / Job No.
- B24VN26014
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-0" X 24'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL ELECTRIC. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 12/30/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/31/2024 | APPLICANT |
| Applicant returned to address corrections | 2/28/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/7/2025 | ANGELICA MARTINEZ |
| Issued | 3/7/2025 | APPLICANT |
| CofO in Progress | 9/5/2025 | VINCENT HANLEY |
| CofO Issued | 9/16/2025 | RUBEN SALAS |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/2/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/3/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 3/5/2025 | THERESA NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/3/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 4/3/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/3/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/11/2025 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/6/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/13/2025 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 5/13/2025 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 5/13/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/16/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/16/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/16/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/16/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 5/23/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/23/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/23/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/28/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 6/2/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/29/2025 | Approved | VINCENT HANLEY |
| Final | 8/29/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/29/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/29/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/29/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 8/29/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 8/29/2025 | Approved | VINCENT HANLEY |
| Final | 9/5/2025 | OK to Issue CofO | VINCENT HANLEY |