5911 N MATILIJA AVE 91401

Certificate Information: 5911 N MATILIJA AVE 91401

Application / Permit
24010-20000-05169
Plan Check / Job No.
B24VN25992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New 16' 3' x 13' Recreation Room. All work per Engineer.
Permit Issued
Issued on 4/21/2025
Issuing Office
Current Status
Issued on 4/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 NAREG ATARIAN
Corrections Issued 12/22/2024 NAREG ATARIAN
Quality Review Completed 12/27/2024 OMID HEDAYAT
Building Plans Picked Up 12/30/2024 APPLICANT
Applicant returned to address corrections 1/16/2025 NAREG ATARIAN
Applicant returned to address corrections 2/26/2025 NAREG ATARIAN
Applicant returned to address corrections 3/10/2025 NAREG ATARIAN
Applicant returned to address corrections 3/14/2025 NAREG ATARIAN
Plan Check Approved 4/21/2025 NAREG ATARIAN
Issued 4/21/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/24/2024 LEE GUILBEAUX
Sewer availability Cleared 12/24/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/24/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/7/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/11/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 7/14/2025 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 8/11/2025 Approved RYAN SALAZAR
Footing/Foundation/Slab 8/11/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 12/8/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Approved RYAN SALAZAR
PLUMBING-Rough 12/8/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/18/2025 Approved RYAN SALAZAR
Green Building Rough 12/18/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/18/2025 Approved RYAN SALAZAR
Wood Frame 12/18/2025 Approved RYAN SALAZAR
Insulation 1/23/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/23/2026 Partial Approval RYAN SALAZAR
Shower Pan 1/23/2026 Approved RYAN SALAZAR
Drywall Nailing 2/19/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 2/23/2026 Approved VINCENT HANLEY
Pre-Inspection 4/1/2026 Approved VINCENT HANLEY
Sewer 4/24/2026 Approved VINCENT HANLEY
Underground Mechanical 4/24/2026 Approved VINCENT HANLEY