22026 1/2 W SATICOY ST 91303

Certificate Information: 22026 1/2 W SATICOY ST 91303

Application / Permit
24010-20000-05154
Plan Check / Job No.
B24VN25943
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-Story Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21. Fully Sprinkled NFPA 13-D --- 1 of 3 ---
Permit Issued
Issued on 4/4/2025
Issuing Office
Current Status
CofO Issued on 4/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 EDWIN ESPIN
Corrections Issued 12/23/2024 EDWIN ESPIN
Quality Review Completed 1/6/2025 HERNAN ARREOLA
Plan Check Approved 2/27/2025 EDWIN ESPIN
Issued 4/4/2025 APPLICANT
CofO in Progress 2/10/2026 CHRIS CHRISTENSEN
Permit Finaled 4/15/2026 JOHN JANSON
CofO Issued 4/15/2026 JOHN JANSON
Permit Finaled 4/15/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/14/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/14/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/16/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 1/24/2025 KURT CORRAL
Senate Bill 9 Cleared 2/4/2025 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/11/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/21/2025 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/21/2025 Approved CHRIS CHRISTENSEN
Sewer 4/21/2025 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 5/2/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 5/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/29/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/29/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 5/29/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/29/2025 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 5/29/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/2/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 6/2/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/2/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 6/4/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/9/2025 Approved CHRIS CHRISTENSEN
Final 8/20/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 8/20/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 8/20/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 8/20/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 2/9/2026 Approved CHRIS CHRISTENSEN
Final 2/9/2026 OK to Issue CofO CHRIS CHRISTENSEN
Service/Power Release 2/9/2026 Approved CHRIS CHRISTENSEN
Smoke Detectors 2/9/2026 Approved CHRIS CHRISTENSEN