7319 N GARDEN GROVE AVE 91335
Certificate Information: 7319 N GARDEN GROVE AVE 91335
- Application / Permit
- 24010-20000-05130
- Plan Check / Job No.
- B24VN25851
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY 27'-11" x 58'-0" DETACHED 2ND DWELLING UNIT PER SB9 2-UNIT DEVELOPEMENT. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 2/7/2025
- Issuing Office
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | ALFRED RAMIREZ |
| Corrections Issued | 1/7/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 1/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 1/13/2025 | APPLICANT |
| Applicant returned to address corrections | 2/5/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 2/7/2025 | ALFRED RAMIREZ |
| Issued | 2/7/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | JUAN ALVARADO |
| CofO in Progress | 5/14/2026 | JOHN JANSON |
| Permit Finaled | 5/15/2026 | JOHN JANSON |
| CofO Issued | 5/15/2026 | JOHN JANSON |
| Permit Finaled | 5/15/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/13/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/22/2025 | JERRY KAO |
| Senate Bill 9 | Cleared | 1/27/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/21/2025 | Approved | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/7/2025 | Conditional Approval | JUAN ALVARADO |
| Special/Order Compliance | 4/7/2025 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/1/2025 | Corrections Issued | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/1/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 7/1/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 7/1/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 7/28/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 7/28/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 9/16/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/22/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 9/22/2025 | Approved | JUAN ALVARADO |
| Insulation | 9/30/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 10/14/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 10/14/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Shower Pan | 10/14/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Drywall Nailing | 10/17/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 10/17/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 10/17/2025 | Approved | JUAN ALVARADO |
| Posting Pre-Inspection | 11/7/2025 | Corrections Issued | JUAN ALVARADO |
| Underground Mechanical | 11/7/2025 | Approved | JUAN ALVARADO |
| Insulation | 12/11/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 3/4/2026 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 3/4/2026 | Approved | JUAN ALVARADO |
| Green Building Final | 3/4/2026 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Not Ready | JUAN ALVARADO |
| Service/Power Release | 3/4/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 3/4/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 3/27/2026 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 3/27/2026 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 3/27/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 3/27/2026 | No Access for Inspection | JUAN ALVARADO |
| Final | 4/7/2026 | Partial Inspection | JUAN ALVARADO |
| Green Building Final | 4/7/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 4/7/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 4/7/2026 | Approved | JUAN ALVARADO |
| Final | 4/13/2026 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 4/13/2026 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 4/21/2026 | Approved | JUAN ALVARADO |
| Final | 4/21/2026 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 4/21/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 4/21/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 4/21/2026 | Approved | JUAN ALVARADO |