17603-17605 W HAMLIN ST 91406
Certificate Information: 17603-17605 W HAMLIN ST 91406
- Application / Permit
- 24010-20000-05120
- Plan Check / Job No.
- B24VN25743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New (2) story SFD per SB9 Two Unit Development per GCS 65852.21 with attached ADU per LAMC 12.22A.33(c) and (e). To be fully sprinklered NFPA 13D.
- Permit Issued
- Issued on 10/2/2025
- Issuing Office
- Current Status
- Issued on 10/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 12/30/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/8/2025 | TU HUA |
| Plan Check Approved | 3/26/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 8/7/2025 | MARCELA FRANQUEZ |
| Issued | 10/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 1/10/2025 | TAL SHEMEN |
| Construction near power lines | Cleared | 1/16/2025 | THERESA NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/17/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/30/2025 | JERRY KAO |
| Senate Bill 9 | Cleared | 3/13/2025 | GEORGIA SMITH |
| ZI | Cleared | 3/13/2025 | GEORGIA SMITH |
| Miscellaneous | Cleared | 3/14/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: NA56905 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/17/2025 | Partial Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 10/24/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/12/2026 | Approved | JON MCHUGH |
| HVAC-Rough | 5/12/2026 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 5/26/2026 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 6/2/2026 | Approved | JON MCHUGH |
| Green Building Rough | 6/2/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 6/2/2026 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/2/2026 | Approved | JON MCHUGH |
| Insulation | 6/10/2026 | Approved | JON MCHUGH |
| Shower Pan | 6/10/2026 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 6/18/2026 | Partial Approval | JON MCHUGH |
| Shower Pan | 6/18/2026 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 6/24/2026 | Approved | IVAN SARABIA |
| Interior/Exterior Lathing | 6/24/2026 | Not Ready for Inspection | IVAN SARABIA |
| Shower Pan | 6/24/2026 | Approved | IVAN SARABIA |
| Special/Order Compliance | 6/24/2026 | Partial Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 7/6/2026 | Approved | JEFFREY PARD |