17406 W CHASE ST 91325
Certificate Information: 17406 W CHASE ST 91325
- Application / Permit
- 24010-20000-05100
- Plan Check / Job No.
- B24VN25546
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan New irregular shaped 43' 6"' x 61' two stories Single Family Dwelling with attached Garage, Porch, and Trellis. NFPA 13D sprinkler required.
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Current Status
- Issued on 5/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | NAREG ATARIAN |
| Corrections Issued | 12/29/2024 | NAREG ATARIAN |
| Quality Review Completed | 12/31/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/8/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 4/17/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 4/24/2025 | NAREG ATARIAN |
| Plan Check Approved | 5/2/2025 | NAREG ATARIAN |
| Issued | 5/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/3/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/6/2025 | RYAN CASTRO |
| Trees in Parkway | Cleared | 2/24/2025 | MIGUEL ORNELAS |
| Permit | Cleared | 2/26/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 3/14/2025 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 5/30/2025 | Corrections Issued | JOSE AVILA |
| Sewer | 5/30/2025 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 6/6/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 6/9/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Steel/Welding | 6/12/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 8/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 8/14/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/27/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 9/24/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/30/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 10/14/2025 | Approved | CHRISTOPHER MORFIN |
| Drywall Nailing | 10/22/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/20/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 11/20/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 1/30/2026 | Approved | CHRISTOPHER ROJAS |