10379 N RINCON AVE 91331

Certificate Information: 10379 N RINCON AVE 91331

Application / Permit
24010-20000-05068
Plan Check / Job No.
B24VN25344
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 2nd s.f.d. per SB9 (2nd unit to be an identical copy of the 1st) PER 2 UNIT DEVELOPMENT CA GOVT CODE 65852.21
Permit Issued
Issued on 1/15/2025
Issuing Office
Current Status
Issued on 1/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 SUNMIN LEE
Corrections Issued 12/21/2024 SUNMIN LEE
Quality Review Completed 12/26/2024 PRANITA SHAH
Applicant returned to address corrections 1/13/2025 SUNMIN LEE
Plan Check Approved 1/15/2025 SUNMIN LEE
Issued 1/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/29/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/29/2024 RYAN CASTRO
Clean Up Green Up Cleared 12/31/2024 ALEX VELA
ZI Cleared 12/31/2024 ALEX VELA
Senate Bill 9 Cleared 1/6/2025 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 1/7/2025 RYAN CASTRO
Sewer availability Cleared 1/7/2025 RYAN CASTRO

Contact Information

Contractor Bg Construction & Remodeling Inc; Lic. No.: 817992-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/28/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/1/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Not Ready for Inspection KEVIN BERBERYAN
Deputy Wood Construction 11/10/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 11/12/2025 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 11/12/2025 Approved MICHEL ABAJAN
Green Building Rough 11/12/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 11/12/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 11/12/2025 Not Ready for Inspection MICHEL ABAJAN
Sewer 11/12/2025 Approved MICHEL ABAJAN
Underground Mechanical 11/12/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/12/2025 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 12/5/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/5/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 12/5/2025 Approved MICHEL ABAJAN
HVAC-Rough 12/5/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 12/5/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/5/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/11/2025 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/18/2025 Approved MICHAEL CORTEZ
Insulation 12/30/2025 Corrections Issued LOUIS ESCOTO
Special/Order Compliance 12/30/2025 Corrections Issued LOUIS ESCOTO
Insulation 1/15/2026 Approved MICHEL ABAJAN
Drywall Nailing 1/23/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/23/2026 Approved MICHEL ABAJAN
Shower Pan 1/23/2026 Approved MICHEL ABAJAN