5050 N LOUISE AVE 91316
Certificate Information: 5050 N LOUISE AVE 91316
- Application / Permit
- 24010-20000-05064
- Plan Check / Job No.
- B24VN25333
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DETACHED ALL ELECTRIC SECOND DWELLING UNIT PER SB 9
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 10/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/19/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/20/2024 | APPLICANT |
| Applicant returned to address corrections | 1/10/2025 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/17/2025 | SARKIS HARABEDIAN |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 9/30/2025 | JON MCHUGH |
| CofO in Progress | 10/1/2025 | SEAN WIRCH |
| Permit Finaled | 10/6/2025 | JOHN JANSON |
| CofO Issued | 10/6/2025 | JOHN JANSON |
| Permit Finaled | 10/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/12/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/15/2025 | CARLOS RAMIREZ |
| Senate Bill 9 | Cleared | 1/16/2025 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2025 | Partial Approval | MORRIS JACKSON |
| Special/Order Compliance | 4/1/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 4/4/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 5/1/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 5/1/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/1/2025 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 5/1/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 5/8/2025 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/8/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | JON MCHUGH |
| Green Building Rough | 5/22/2025 | Approved | JON MCHUGH |
| Insulation | 5/22/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 5/22/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 5/22/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/22/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 5/27/2025 | Partial Approval | SCOTT SOBEL |
| Drywall Nailing | 6/2/2025 | Approved | JON MCHUGH |
| Final | 7/28/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 7/28/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 7/28/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 7/28/2025 | Approved | JON MCHUGH |
| Final | 9/3/2025 | Corrections Issued | MORRIS JACKSON |
| Service/Power Release | 9/3/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 9/16/2025 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 9/16/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 9/30/2025 | Approved | JON MCHUGH |
| Final | 9/30/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 9/30/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 9/30/2025 | Approved | JON MCHUGH |
| Service/Power Release | 9/30/2025 | Approved | JON MCHUGH |