5050 N LOUISE AVE 91316

Certificate Information: 5050 N LOUISE AVE 91316

Application / Permit
24010-20000-05064
Plan Check / Job No.
B24VN25333
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW DETACHED ALL ELECTRIC SECOND DWELLING UNIT PER SB 9
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
CofO Issued on 10/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 JEROME MAGAT PALMA
Corrections Issued 12/19/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/20/2024 APPLICANT
Applicant returned to address corrections 1/10/2025 JEROME MAGAT PALMA
Plan Check Approved 1/17/2025 SARKIS HARABEDIAN
Issued 1/17/2025 APPLICANT
CofO in Progress 9/30/2025 JON MCHUGH
CofO in Progress 10/1/2025 SEAN WIRCH
Permit Finaled 10/6/2025 JOHN JANSON
CofO Issued 10/6/2025 JOHN JANSON
Permit Finaled 10/6/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/12/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/12/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/15/2025 CARLOS RAMIREZ
Sewer availability Cleared 1/15/2025 CARLOS RAMIREZ
Senate Bill 9 Cleared 1/16/2025 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2025 Partial Approval MORRIS JACKSON
Special/Order Compliance 4/1/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 4/4/2025 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 5/1/2025 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Approved JON MCHUGH
HVAC-Rough 5/1/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 5/1/2025 Corrections Issued JON MCHUGH
Rough-Elec/Plmb/HVAC 5/1/2025 Not Ready for Inspection JON MCHUGH
Shower Pan 5/1/2025 Approved JON MCHUGH
Interior/Exterior Lathing 5/8/2025 Partial Approval JON MCHUGH
Rough-Elec/Plmb/HVAC 5/8/2025 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 5/22/2025 Approved JON MCHUGH
Green Building Rough 5/22/2025 Approved JON MCHUGH
Insulation 5/22/2025 Approved JON MCHUGH
Interior/Exterior Lathing 5/22/2025 Approved JON MCHUGH
PLUMBING-Rough 5/22/2025 Approved JON MCHUGH
Verify Sprinkler Sign Off 5/22/2025 Approved JON MCHUGH
Drywall Nailing 5/27/2025 Partial Approval SCOTT SOBEL
Drywall Nailing 6/2/2025 Approved JON MCHUGH
Final 7/28/2025 Corrections Issued JON MCHUGH
Green Building Final 7/28/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved JON MCHUGH
Service/Power Release 7/28/2025 Not Ready for Inspection JON MCHUGH
Smoke Detectors 7/28/2025 Approved JON MCHUGH
Final 9/3/2025 Corrections Issued MORRIS JACKSON
Service/Power Release 9/3/2025 Not Ready for Inspection MORRIS JACKSON
Final 9/16/2025 Corrections Issued JON MCHUGH
Service/Power Release 9/16/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 9/30/2025 Approved JON MCHUGH
Final 9/30/2025 OK to Issue CofO JON MCHUGH
HVAC-Final 9/30/2025 Approved JON MCHUGH
PLUMBING-Final 9/30/2025 Approved JON MCHUGH
Service/Power Release 9/30/2025 Approved JON MCHUGH