12116 W IVY PL 90064
Certificate Information: 12116 W IVY PL 90064
- Application / Permit
- 24010-20000-05051
- Plan Check / Job No.
- B24VN25192
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/16/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/19/2024 | APPLICANT |
| Plan Check Approved | 2/20/2025 | YAQUB MIRZA |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 12/24/2025 | KIRK SANDERS |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/30/2024 | RICHARD WOO |
| Address approval | Cleared | 1/4/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 1/8/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 2/11/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Vision Adu Llc; Lic. No.: 1115842-B | 405 S MISSION DR SAN GABRIEL, CA 91776 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/2/2025 | Partial Approval | WILBER ROSALES |
| Footing/Foundation/Slab | 4/8/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 5/2/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Rough | 5/2/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 5/2/2025 | Corrections Issued | WILBER ROSALES |
| BUILDING-Rough-Frame | 5/8/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 5/8/2025 | Approved | WILBER ROSALES |
| Insulation | 5/8/2025 | Corrections Issued | WILBER ROSALES |
| Interior/Exterior Lathing | 5/8/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 5/14/2025 | Corrections Issued | WILBER ROSALES |
| Shower Pan | 6/18/2025 | Corrections Issued | WILBER ROSALES |
| Sewer | 7/10/2025 | Approved | WILBER ROSALES |
| Underground Mechanical | 7/10/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/18/2025 | Corrections Issued | KIRK SANDERS |
| Final | 9/18/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/18/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 9/18/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/18/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Not Required | KIRK SANDERS |
| Service/Power Release | 9/18/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 9/18/2025 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 9/18/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 12/4/2025 | Partial Approval | KIRK SANDERS |
| Final | 12/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 12/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 12/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| Final | 12/15/2025 | Corrections Issued | KIRK SANDERS |
| Service/Power Release | 12/15/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 12/18/2025 | Approved | ANDREW NAVE |
| Final | 12/18/2025 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 12/18/2025 | Not Ready for Inspection | ANDREW NAVE |
| Final | 12/24/2025 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 12/24/2025 | Approved | KIRK SANDERS |