12116 W IVY PL 90064

Certificate Information: 12116 W IVY PL 90064

Application / Permit
24010-20000-05051
Plan Check / Job No.
B24VN25192
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/20/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/16/2024 JEROME MAGAT PALMA
Corrections Issued 12/16/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/19/2024 APPLICANT
Plan Check Approved 2/20/2025 YAQUB MIRZA
Issued 2/20/2025 APPLICANT
CofO in Progress 12/24/2025 KIRK SANDERS
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 12/30/2024 RICHARD WOO
Address approval Cleared 1/4/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 1/8/2025 LIAM ODONOVAN
Sewer availability Cleared 1/8/2025 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 1/11/2025 LIAM ODONOVAN
Construction near power lines Cleared 2/11/2025 RIDWAN HARDY

Contact Information

Contractor Vision Adu Llc; Lic. No.: 1115842-B 405 S MISSION DR      SAN GABRIEL, CA 91776
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/2/2025 Partial Approval WILBER ROSALES
Footing/Foundation/Slab 4/8/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 5/2/2025 Corrections Issued WILBER ROSALES
HVAC-Rough 5/2/2025 Corrections Issued WILBER ROSALES
PLUMBING-Rough 5/2/2025 Corrections Issued WILBER ROSALES
BUILDING-Rough-Frame 5/8/2025 Corrections Issued WILBER ROSALES
Green Building Rough 5/8/2025 Approved WILBER ROSALES
Insulation 5/8/2025 Corrections Issued WILBER ROSALES
Interior/Exterior Lathing 5/8/2025 Approved WILBER ROSALES
Drywall Nailing 5/14/2025 Corrections Issued WILBER ROSALES
Shower Pan 6/18/2025 Corrections Issued WILBER ROSALES
Sewer 7/10/2025 Approved WILBER ROSALES
Underground Mechanical 7/10/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/18/2025 Approved KIRK SANDERS
ELECTRICAL-Final 9/18/2025 Corrections Issued KIRK SANDERS
Final 9/18/2025 Corrections Issued KIRK SANDERS
Green Building Final 9/18/2025 Approved KIRK SANDERS
HVAC-Final 9/18/2025 Approved KIRK SANDERS
PLUMBING-Final 9/18/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Required KIRK SANDERS
Service/Power Release 9/18/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 9/18/2025 Approved KIRK SANDERS
Verify Sprinkler Sign Off 9/18/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/4/2025 Partial Approval KIRK SANDERS
Final 12/4/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 12/4/2025 Not Ready for Inspection KIRK SANDERS
Service/Power Release 12/4/2025 Not Ready for Inspection KIRK SANDERS
Final 12/15/2025 Corrections Issued KIRK SANDERS
Service/Power Release 12/15/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 12/18/2025 Approved ANDREW NAVE
Final 12/18/2025 Corrections Issued ANDREW NAVE
Service/Power Release 12/18/2025 Not Ready for Inspection ANDREW NAVE
Final 12/24/2025 OK to Issue CofO KIRK SANDERS
Service/Power Release 12/24/2025 Approved KIRK SANDERS