2534 S CLYDE AVE 90016

Certificate Information: 2534 S CLYDE AVE 90016

Application / Permit
24010-20000-05042
Plan Check / Job No.
B24VN25119
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'-6" X 30' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 SELLA BENYAMIN
Corrections Issued 12/17/2024 SELLA BENYAMIN
Quality Review Completed 12/17/2024 STEVEN KIM
Building Plans Picked Up 12/19/2024 APPLICANT
Plan Check Approved 1/23/2025 SELLA BENYAMIN
Issued 1/24/2025 APPLICANT
CofO in Progress 8/4/2025 ARTHUR NEGRETE
Permit Finaled 8/24/2025 DEROLD HAUFF
CofO Issued 8/24/2025 DEROLD HAUFF
Permit Finaled 8/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/23/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/23/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 12/23/2024 CELINA MORENO
Sewer availability Cleared 12/23/2024 JEANIE LAM
Hold Cleared 2/7/2025 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 2/26/2025 Partial Inspection ALEX COLIN
Footing/Foundation/Slab 2/28/2025 Corrections Issued LUIS CASTRO
Special/Order Compliance 3/3/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/4/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/13/2025 Partial Inspection ALEX COLIN
Wood Frame 3/25/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 4/23/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/23/2025 Approved ARTHUR NEGRETE
Sewer 4/23/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/1/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/1/2025 Approved ARTHUR NEGRETE
Insulation 5/5/2025 Approved ALEX COLIN
Drywall Nailing 5/9/2025 Approved ALEX COLIN
Shower Pan 5/30/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 7/8/2025 Approved ARTHUR NEGRETE
Service/Power Release 7/8/2025 Approved ARTHUR NEGRETE
Green Building Rough 7/17/2025 Approved ARTHUR NEGRETE
HVAC-Final 7/17/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 7/17/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/28/2025 Partial Inspection ARTHUR NEGRETE
Final 7/28/2025 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 7/28/2025 Partial Approval ARTHUR NEGRETE
Green Building Final 7/28/2025 Not Ready for Inspection ARTHUR NEGRETE
MERV13>=Final 7/28/2025 Not Ready for Inspection ARTHUR NEGRETE
MERV13>=Rough 7/28/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/28/2025 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 7/28/2025 Not Ready for Inspection ARTHUR NEGRETE
BUILDING-Rough-Frame 7/31/2025 Partial Approval ARTHUR NEGRETE
Final 7/31/2025 Partial Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 7/31/2025 Approved ARTHUR NEGRETE
Green Building Final 7/31/2025 Approved ARTHUR NEGRETE
MERV13>=Final 7/31/2025 Approved ARTHUR NEGRETE
MERV13>=Rough 7/31/2025 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 7/31/2025 Partial Approval ARTHUR NEGRETE
BUILDING-Rough-Frame 8/4/2025 Approved ARTHUR NEGRETE
Final 8/4/2025 OK to Issue CofO ARTHUR NEGRETE
Verify Sprinkler Sign Off 8/4/2025 Approved ARTHUR NEGRETE