6948 N AMESTOY AVE 91406
Certificate Information: 6948 N AMESTOY AVE 91406
- Application / Permit
- 24010-20000-05029
- Plan Check / Job No.
- B24VN25041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW 1-STORY SINGLE FAMILY DWELLING per SB9 Two-Unit Development Ca Govt Code 65852.21 NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 3/6/2025
- Issuing Office
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JAD BASMA |
| Corrections Issued | 12/24/2024 | JAD BASMA |
| Quality Review Completed | 12/24/2024 | PRANITA SHAH |
| Plan Check Approved | 3/5/2025 | JAD BASMA |
| Plan Check Approved | 3/6/2025 | JAD BASMA |
| Issued | 3/6/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | JON MCHUGH |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
| CofO Issued | 2/24/2026 | JOHN JANSON |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/30/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/30/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 1/13/2025 | ERNEST TSE |
| Senate Bill 9 | Cleared | 1/13/2025 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 2/4/2025 | JERRY KAO |
| Construction near power lines | Cleared | 2/13/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/8/2025 | Partial Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 4/16/2025 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 4/17/2025 | Conditional Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 5/14/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 6/13/2025 | Partial Approval | JON MCHUGH |
| Sewer | 6/13/2025 | Approved | JON MCHUGH |
| Underground Mechanical | 6/13/2025 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 6/17/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 7/11/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 7/11/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 7/11/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JON MCHUGH |
| Green Building Rough | 7/18/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 7/18/2025 | Approved | JON MCHUGH |
| Insulation | 7/25/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/31/2025 | Approved | JON MCHUGH |
| Shower Pan | 8/7/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 8/19/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 8/29/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/15/2026 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 1/15/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 1/15/2026 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 1/21/2026 | Not Ready for Inspection | JON MCHUGH |
| Final | 1/21/2026 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 1/21/2026 | Approved | JON MCHUGH |
| HVAC-Final | 1/21/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/21/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 1/21/2026 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 1/21/2026 | Approved | JON MCHUGH |
| Final | 1/26/2026 | Partial Approval | JON MCHUGH |
| Service/Power Release | 1/26/2026 | Approved | JON MCHUGH |
| Final | 1/27/2026 | OK to Issue CofO | JON MCHUGH |