12613 W LAZARD ST 91342
Certificate Information: 12613 W LAZARD ST 91342
- Application / Permit
- 24010-20000-05016
- Plan Check / Job No.
- B24VN24934
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Proposed 2-Story DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/9/2025
- Issuing Office
- Current Status
- CofO Issued on 10/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JESSE VIDUYA |
| Corrections Issued | 1/2/2025 | JESSE VIDUYA |
| Quality Review Completed | 1/7/2025 | CHAD DOI |
| Applicant returned to address corrections | 3/26/2025 | JESSE VIDUYA |
| Plan Check Approved | 4/9/2025 | JESSE VIDUYA |
| Issued | 4/9/2025 | APPLICANT |
| CofO in Progress | 9/25/2025 | KEVIN BERBERYAN |
| No Progress | 10/14/2025 | RAUL OLAGI |
| CofO in Progress | 10/14/2025 | RAUL OLAGI |
| CofO in Progress | 10/22/2025 | KEVIN BERBERYAN |
| CofO in Progress | 10/22/2025 | KEVIN BERBERYAN |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
| CofO Issued | 10/24/2025 | RUBEN SALAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/10/2025 | RYAN CASTRO |
| GPI Written Notices | Cleared | 3/26/2025 | JESSE VIDUYA |
| Grading Pre-Inspection | Cleared | 3/26/2025 | JESSE VIDUYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 5/14/2025 | Partial Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/26/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/26/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/26/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 6/26/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/26/2025 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | KEVIN BERBERYAN |
| Insulation | 6/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 7/2/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 7/2/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/2/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/3/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 9/3/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/3/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 9/17/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 9/25/2025 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 10/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 10/20/2025 | Approved | KEVIN BERBERYAN |
| Final | 10/22/2025 | OK to Issue CofO | KEVIN BERBERYAN |