12613 W LAZARD ST 91342

Certificate Information: 12613 W LAZARD ST 91342

Application / Permit
24010-20000-05016
Plan Check / Job No.
B24VN24934
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Proposed 2-Story DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/9/2025
Issuing Office
Current Status
CofO Issued on 10/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 JESSE VIDUYA
Corrections Issued 1/2/2025 JESSE VIDUYA
Quality Review Completed 1/7/2025 CHAD DOI
Applicant returned to address corrections 3/26/2025 JESSE VIDUYA
Plan Check Approved 4/9/2025 JESSE VIDUYA
Issued 4/9/2025 APPLICANT
CofO in Progress 9/25/2025 KEVIN BERBERYAN
No Progress 10/14/2025 RAUL OLAGI
CofO in Progress 10/14/2025 RAUL OLAGI
CofO in Progress 10/22/2025 KEVIN BERBERYAN
CofO in Progress 10/22/2025 KEVIN BERBERYAN
Permit Finaled 10/24/2025 RUBEN SALAS
CofO Issued 10/24/2025 RUBEN SALAS
Permit Finaled 10/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/9/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/9/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/10/2025 RYAN CASTRO
Sewer availability Cleared 1/10/2025 RYAN CASTRO
GPI Written Notices Cleared 3/26/2025 JESSE VIDUYA
Grading Pre-Inspection Cleared 3/26/2025 JESSE VIDUYA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/13/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 5/14/2025 Corrections Issued KEVIN BERBERYAN
Special/Order Compliance 5/14/2025 Partial Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 5/19/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 6/26/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 6/26/2025 Approved KEVIN BERBERYAN
Green Building Rough 6/26/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 6/26/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 6/26/2025 Approved KEVIN BERBERYAN
Deputy Wood Construction 6/27/2025 Conditional Approval KEVIN BERBERYAN
Insulation 6/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
Drywall Nailing 7/2/2025 Approved KEVIN BERBERYAN
Green Building Rough 7/2/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 7/2/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 9/3/2025 Approved KEVIN BERBERYAN
Final 9/3/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 9/3/2025 Approved KEVIN BERBERYAN
Green Building Final 9/3/2025 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 9/3/2025 Approved KEVIN BERBERYAN
Smoke Detectors 9/3/2025 Approved KEVIN BERBERYAN
Final 9/17/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 9/17/2025 Approved KEVIN BERBERYAN
Special/Order Compliance 9/25/2025 Corrections Issued KEVIN BERBERYAN
Special/Order Compliance 10/10/2025 Corrections Issued KEVIN BERBERYAN
Special/Order Compliance 10/20/2025 Approved KEVIN BERBERYAN
Final 10/22/2025 OK to Issue CofO KEVIN BERBERYAN