1705 N ECHO PARK AVE 90026
Certificate Information: 1705 N ECHO PARK AVE 90026
- Application / Permit
- 24010-20000-05013
- Plan Check / Job No.
- B24VN24890
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED IRREG SHAPED ACCESSORY DWELLING UNIT PER GC S66323(a)(2), ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/14/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/19/2024 | APPLICANT |
| Issued | 4/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 1/2/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 1/7/2025 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/23/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/18/2025 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/25/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 9/3/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 9/3/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/5/2025 | Corrections Issued | ALEX COLIN |
| Rough-Elec/Plmb/HVAC | 9/8/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 10/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 10/20/2025 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/22/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/22/2025 | Approved | HAMIK HARTOUNIAN |