1331 E 48TH PL 90011

Certificate Information: 1331 E 48TH PL 90011

Application / Permit
24010-20000-04991
Plan Check / Job No.
B24VN24720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW SINGLE FAMILY DWELLING AT REAR.
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 KEVIN MORALES
Corrections Issued 12/17/2024 KEVIN MORALES
Quality Review Completed 12/18/2024 EUGENE BARBEAU
Plan Check Approved 1/24/2025 KEVIN MORALES
Issued 1/24/2025 APPLICANT
CofO in Progress 4/1/2026 ALEJANDRO DE ARTOLA
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/20/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 12/30/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/7/2025 WALLIE JONG
Sewer availability Cleared 1/7/2025 WALLIE JONG
Hydrant and Access approval Cleared 1/15/2025 PATRICK PEREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/3/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/3/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/4/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/1/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/24/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/24/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/24/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/30/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 7/30/2025 Approved RONNIE MEDINA
Underground Mechanical 2/11/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/24/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 3/24/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/24/2026 Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/24/2026 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 3/24/2026 Approved ALEJANDRO DE ARTOLA
Final 3/25/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/25/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/25/2026 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 3/25/2026 Approved ALEJANDRO DE ARTOLA
Final 4/1/2026 OK to Issue CofO ALEJANDRO DE ARTOLA