19227 W FRIAR ST 91335
Certificate Information: 19227 W FRIAR ST 91335
- Application / Permit
- 24010-20000-04983
- Plan Check / Job No.
- B24VN24687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) 1-STORY SINGLE FAMILY DWELLING PER SENATE BILL 9 TWO-UNIT DEVELOPMENT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | RARES BODEA |
| Corrections Issued | 12/18/2024 | RARES BODEA |
| Quality Review Completed | 12/18/2024 | STEVEN KIM |
| Plan Check Approved | 4/25/2025 | RARES BODEA |
| Issued | 5/13/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | MORRIS JACKSON |
| Permit Finaled | 5/1/2026 | JOHN JANSON |
| CofO Issued | 5/1/2026 | JOHN JANSON |
| Permit Finaled | 5/1/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 12/20/2024 | BRENNEN OBETO |
| Senate Bill 9 | Cleared | 1/16/2025 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 4/1/2025 | PATRICK PEREZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Dynamic General Contractors Inc; Lic. No.: 591466-B | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/22/2025 | Partial Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 11/10/2025 | Approved | MORRIS JACKSON |
| Sewer | 11/10/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 1/14/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/22/2026 | Partial Approval | MORRIS JACKSON |
| Underground Mechanical | 1/22/2026 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/30/2026 | Approved | MORRIS JACKSON |
| Green Building Rough | 1/30/2026 | Approved | MORRIS JACKSON |
| HVAC-Rough | 1/30/2026 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 1/30/2026 | Approved | MORRIS JACKSON |
| Wood Frame | 1/30/2026 | Partial Approval | MORRIS JACKSON |
| Insulation | 2/4/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 2/9/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/9/2026 | Approved | DAVID SCANTLIN |
| Shower Pan | 2/9/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/12/2026 | Approved | MORRIS JACKSON |
| HVAC-Final | 3/12/2026 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 3/12/2026 | Approved | MORRIS JACKSON |
| Service/Power Release | 3/12/2026 | Approved | MORRIS JACKSON |
| Final | 3/16/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 3/16/2026 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 3/16/2026 | Approved | MORRIS JACKSON |
| Final | 3/23/2026 | OK to Issue CofO | MORRIS JACKSON |