10534 W KLING ST 91602

Certificate Information: 10534 W KLING ST 91602

Application / Permit
24010-20000-04972
Plan Check / Job No.
B24VN24603
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-7 1/2"X 19'-8 1/2" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER GC 66323(a)(2) NPFA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
Issued on 6/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/3/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 KAMYAR EMAMI
Corrections Issued 12/9/2024 KAMYAR EMAMI
Applicant returned to address corrections 1/29/2025 OMAR GARNICA
Applicant returned to address corrections 4/2/2025 KAMYAR EMAMI
Plan Check Approved 4/7/2025 KAMYAR EMAMI
Issued 6/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/17/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/30/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/30/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/30/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 3/7/2025 RIDWAN HARDY
Hydrant and Access approval Cleared 4/1/2025 KURT CORRAL

Contact Information

Contractor Quantum Construction & Design; Lic. No.: 1061867-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/8/2025 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/21/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/29/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/5/2025 No Access for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 No Access for Inspection JOSE AVILA
HVAC-Rough 12/5/2025 No Access for Inspection JOSE AVILA
PLUMBING-Rough 12/5/2025 No Access for Inspection JOSE AVILA
PLUMBING-Rough 12/12/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 12/22/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/22/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 12/22/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 12/22/2025 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 1/13/2026 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/15/2026 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 1/22/2026 Approved JOSE AVILA
ELECTRICAL-Rough 2/3/2026 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/3/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/3/2026 Approved ROBERTO PALACIOS-LOPEZ
MERV13>=Rough 2/3/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/3/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/23/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/23/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/26/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/26/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/3/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/16/2026 Conditional Approval GAREN HAYRAPETYAN
Structural Steel Frame 4/16/2026 Partial Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/1/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 5/1/2026 Approved WAYNE REGESTER
BUILDING-Rough-Frame 5/6/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/6/2026 Partial Approval GAREN HAYRAPETYAN
Insulation 5/20/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/20/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 5/21/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 5/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ