10534 W KLING ST 91602
Certificate Information: 10534 W KLING ST 91602
- Application / Permit
- 24010-20000-04972
- Plan Check / Job No.
- B24VN24603
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-7 1/2"X 19'-8 1/2" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER GC 66323(a)(2) NPFA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- Issued on 6/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2024 | KAMYAR EMAMI |
| Corrections Issued | 12/9/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 1/29/2025 | OMAR GARNICA |
| Applicant returned to address corrections | 4/2/2025 | KAMYAR EMAMI |
| Plan Check Approved | 4/7/2025 | KAMYAR EMAMI |
| Issued | 6/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/30/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 3/7/2025 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/1/2025 | KURT CORRAL |
Contact Information
| Contractor | Quantum Construction & Design; Lic. No.: 1061867-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/8/2025 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/21/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/5/2025 | No Access for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | No Access for Inspection | JOSE AVILA |
| HVAC-Rough | 12/5/2025 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 12/5/2025 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 12/12/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 1/13/2026 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 1/15/2026 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 1/22/2026 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Rough | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/23/2026 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 3/23/2026 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/26/2026 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 3/26/2026 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/16/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Structural Steel Frame | 4/16/2026 | Partial Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/1/2026 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/1/2026 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 5/6/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/6/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 5/20/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/20/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/21/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 5/26/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/26/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |