1021 W CHILDS WAY 90089

Certificate Information: 1021 W CHILDS WAY 90089

Application / Permit
24010-20000-04944
Plan Check / Job No.
B24VN22109
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EPLAN New Type II-B Clubhouse building, nfpa-13 fire sprinklersm throughout, All work per engineering
Permit Issued
Issued on 8/1/2025
Issuing Office
Metro
Current Status
Issued on 8/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 RARES BODEA
Corrections Issued 12/11/2024 RARES BODEA
Quality Review Completed 12/12/2024 STEVEN KIM
Applicant returned to address corrections 1/15/2025 RARES BODEA
Applicant returned to address corrections 1/30/2025 RARES BODEA
Applicant returned to address corrections 2/20/2025 RARES BODEA
Applicant returned to address corrections 2/24/2025 RARES BODEA
Applicant returned to address corrections 3/10/2025 RARES BODEA
Plan Check Approved 7/30/2025 RARES BODEA
Plan Check Approved 7/31/2025 RARES BODEA
No Progress 7/31/2025 RARES BODEA
Plan Check Approved 7/31/2025 RARES BODEA
No Progress 7/31/2025 RARES BODEA
Plan Check Approved 7/31/2025 RARES BODEA
No Progress 7/31/2025 RARES BODEA
Plan Check Approved 7/31/2025 RARES BODEA
No Progress 8/1/2025 RARES BODEA
Plan Check Approved 8/1/2025 RARES BODEA
Issued 8/1/2025 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 12/20/2024 DANIEL CORONADO
ZA Case Cleared 12/20/2024 DANIEL CORONADO
ZA Case Cleared 12/20/2024 DANIEL CORONADO
ZA Case Cleared 12/20/2024 DANIEL CORONADO
Miscellaneous Cleared 2/27/2025 MATIAS FARFAN
Specific Plan Cleared 2/27/2025 MANERI ROMAN
ZA Case Cleared 2/27/2025 MANERI ROMAN
Hydrant and Access approval Cleared 3/7/2025 JOHN CONNEALLY
Redevelopment Project Area Cleared 3/7/2025 YASMINE BASHIRI
ZA Case Cleared 3/13/2025 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 3/24/2025 ADRIAN SANCHEZ
Sewer availability Cleared 3/26/2025 ADRIAN SANCHEZ
Fire Marshal Fire Life Safety Cleared 4/10/2025 ANDREW KO
Low Impact Development (LID) Cleared 5/5/2025 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/30/2025 MATIAS FARFAN
DAS Clearance Cleared 7/11/2025 RARES BODEA
Green Code Cleared 7/16/2025 RARES BODEA
Highway dedication Cleared 7/23/2025 TREVOR QUAN

Contact Information

Contractor Clark Construction Group California Lp; Lic. No.: 839892-B 7900 WESTPARK DRIVE SUITE T300      MCLEAN, VA 22102
Engineer Timmers,, Matthew; Lic. No.: S5560 950 S. GRAND AVE 4TH FLR      LOS ANGELES, CA 90015

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2025 Partial Approval JOEY BUCHANAN
METHANE-Barrier 8/12/2025 Approved JOEY BUCHANAN
METHANE-Subgrade 8/12/2025 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 8/13/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 8/14/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 8/22/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 8/25/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/3/2025 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 9/8/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/9/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/10/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/11/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/12/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/16/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/17/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/18/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/22/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/23/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/24/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 9/30/2025 Conditional Approval JOEY BUCHANAN
Green Building Rough 9/30/2025 Approved JOEY BUCHANAN
METHANE-Rough 9/30/2025 Not Ready for Inspection JOEY BUCHANAN
Structural Steel Frame 9/30/2025 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 9/30/2025 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/1/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/2/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/3/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/6/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/8/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/9/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/9/2025 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/9/2025 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/10/2025 Conditional Approval LARRY ARNICK
Light Gage Steel Frame 10/10/2025 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 10/10/2025 Partial Approval LARRY ARNICK
METHANE-Rough 10/17/2025 Approved JOEY BUCHANAN
Reinforced Masonry Frame 10/17/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 10/23/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 10/29/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 10/31/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 11/4/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 11/7/2025 Partial Approval JOEY BUCHANAN
Reinforced Masonry Frame 11/18/2025 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 11/21/2025 Not Ready for Inspection JOEY BUCHANAN
Drywall Nailing 11/25/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 12/4/2025 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 12/9/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 12/30/2025 Not Ready for Inspection JOEY BUCHANAN
Insulation 12/30/2025 Not Ready for Inspection JOEY BUCHANAN
Reinforced Concrete Frame 12/30/2025 Partial Approval JOEY BUCHANAN
Piling/Pier/Caisson 1/21/2026 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 1/23/2026 Partial Inspection JOEY BUCHANAN
Footing/Foundation/Slab 1/29/2026 Not Ready for Inspection JOEY BUCHANAN
T-Bar Ceiling 2/19/2026 Partial Approval JOEY BUCHANAN
T-Bar Ceiling 3/17/2026 Approved JOEY BUCHANAN