14217 W CANTLAY ST 91405
Certificate Information: 14217 W CANTLAY ST 91405
- Application / Permit
- 24010-20000-04925
- Plan Check / Job No.
- B24VN24323
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-0" X 30'-3" DETACHED ACCESSORY DWELLING UNIT W/ 4'-6" X 10'-8" PORCH PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Current Status
- Issued on 2/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 12/7/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/9/2024 | APPLICANT |
| Issued | 2/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/27/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 1/28/2025 | GEVORK KARAPETYAN |
| Roof/Waste drainage to street | Cleared | 2/14/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/17/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/17/2025 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/24/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/3/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/7/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 7/7/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/7/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 7/7/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/7/2025 | Approved | VINCENT HANLEY |
| Insulation | 7/17/2025 | Corrections Issued | MICHAEL CORTEZ |
| Insulation | 7/23/2025 | Corrections Issued | MICHAEL CORTEZ |
| Drywall Nailing | 8/8/2025 | Approved | VINCENT HANLEY |
| Insulation | 8/8/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 10/8/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 10/16/2025 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/6/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 11/6/2025 | Approved | VINCENT HANLEY |
| Green Building Final | 4/17/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/20/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/20/2026 | Approved | VINCENT HANLEY |
| Final | 4/20/2026 | Partial Inspection | VINCENT HANLEY |
| HVAC-Final | 4/20/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/20/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 4/20/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/20/2026 | Approved | VINCENT HANLEY |
| Green Building Final | 4/21/2026 | Approved | JOSE AVILA |