14217 W CANTLAY ST 91405

Certificate Information: 14217 W CANTLAY ST 91405

Application / Permit
24010-20000-04925
Plan Check / Job No.
B24VN24323
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-0" X 30'-3" DETACHED ACCESSORY DWELLING UNIT W/ 4'-6" X 10'-8" PORCH PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/14/2025
Issuing Office
Current Status
Issued on 2/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/4/2024 ARTIN ZARUKIAN
Corrections Issued 12/7/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/9/2024 APPLICANT
Issued 2/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/11/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/27/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/27/2024 EDGAR ALCARAZ
Construction near power lines Cleared 1/28/2025 GEVORK KARAPETYAN
Roof/Waste drainage to street Cleared 2/14/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/17/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 4/17/2025 Partial Approval VINCENT HANLEY
Sewer 4/17/2025 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 4/24/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/24/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/3/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/7/2025 Partial Approval VINCENT HANLEY
Green Building Rough 7/7/2025 Approved VINCENT HANLEY
HVAC-Rough 7/7/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/7/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 7/7/2025 Approved VINCENT HANLEY
Underground Mechanical 7/7/2025 Approved VINCENT HANLEY
Insulation 7/17/2025 Corrections Issued MICHAEL CORTEZ
Insulation 7/23/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 8/8/2025 Approved VINCENT HANLEY
Insulation 8/8/2025 Approved VINCENT HANLEY
Shower Pan 10/8/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 10/16/2025 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 11/6/2025 Approved VINCENT HANLEY
Shower Pan 11/6/2025 Approved VINCENT HANLEY
Green Building Final 4/17/2026 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/20/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 4/20/2026 Approved VINCENT HANLEY
Final 4/20/2026 Partial Inspection VINCENT HANLEY
HVAC-Final 4/20/2026 Approved VINCENT HANLEY
PLUMBING-Final 4/20/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/20/2026 Approved VINCENT HANLEY
Smoke Detectors 4/20/2026 Approved VINCENT HANLEY
Green Building Final 4/21/2026 Approved JOSE AVILA