14422-14424 W TYLER ST 91342
Certificate Information: 14422-14424 W TYLER ST 91342
- Application / Permit
- 24010-20000-04918
- Plan Check / Job No.
- B24VN24249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story SFD and ADU. 1st story Accessory Dewlling Unit (41'-3" x 27'-10") per GC66323 (a)(1) and 2nd story Single Family Dwelling unit (27'-10" X 26'-6") per SB9 Two-Unit Development Ca Govt Code 65852.21 NFPA-13D Sprinklers throughout
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | EDWARD MEHRABIAN |
| Corrections Issued | 12/16/2024 | EDWARD MEHRABIAN |
| Quality Review Completed | 12/24/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/6/2025 | APPLICANT |
| Applicant returned to address corrections | 5/13/2025 | EDWARD MEHRABIAN |
| Plan Check Approved | 5/15/2025 | EDWARD MEHRABIAN |
| Issued | 5/16/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/9/2025 | RYAN CASTRO |
| Address approval | Cleared | 2/27/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 2/28/2025 | RYAN CASTRO |
| Watercourse | Cleared | 2/28/2025 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 3/4/2025 | KENNETH FRASER |
| Senate Bill 9 | Cleared | 3/10/2025 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/15/2025 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 7/15/2025 | Partial Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 7/22/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/11/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 8/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 8/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 8/29/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 9/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 9/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 9/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/20/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 10/20/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/20/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| Shower Pan | 10/28/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 10/28/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 11/5/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 1/8/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |