10561 N HILLHAVEN AVE 91042
Certificate Information: 10561 N HILLHAVEN AVE 91042
- Application / Permit
- 24010-20000-04909
- Plan Check / Job No.
- B24VN24175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- Issued on 3/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/5/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/10/2024 | APPLICANT |
| No Progress | 3/10/2025 | SEWADA ZADOORAN MILAGARDI |
| Applicant returned to address corrections | 3/10/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/21/2025 | GURUNATH NESARAJAH |
| Issued | 3/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/8/2025 | RYAN CASTRO |
| Private sewage disp. approval | Cleared | 3/12/2025 | MICHAEL TEMPLE |
| GPI Written Notices | Cleared | 3/21/2025 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 3/21/2025 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/17/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/30/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/13/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 5/13/2025 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 8/21/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/21/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/21/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 8/28/2025 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 8/28/2025 | Approved | WILLIAM WREN |
| Wood Frame | 8/28/2025 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 10/16/2025 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 10/16/2025 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 10/16/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 12/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 12/29/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/26/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 3/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 3/26/2026 | Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 3/26/2026 | Approved | NICHOLAS TROWBRIDGE |