ePlan CONVERT ATTIC AREA WITH 2-STORY ADDITION TO ADU AND NEW EXTERIOR STAIR PER LAMC 12.22 A.33 (c)(e) ***COMPLY WITH DEPARTMENT ORDER***
Permit Issued
Issued on 6/9/2025
Issuing Office
Metro
Current Status
CofO in Progress on 4/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/2/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 KHUONG TRUONG
Corrections Issued 12/19/2024 KHUONG TRUONG
Quality Review Completed 12/23/2024 PRANITA SHAH
Applicant returned to address corrections 5/14/2025 KHUONG TRUONG
Plan Check Approved 5/28/2025 KHUONG TRUONG
Issued 6/9/2025 APPLICANT
CofO in Progress 4/2/2026 DANIEL GUEVARA

Permit Application Clearance Information

Address approval Cleared 2/15/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/15/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/21/2025 TREVOR QUAN
Sewer availability Cleared 2/21/2025 TREVOR QUAN
Community Plan Implem. Overlay Cleared 5/8/2025 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: NA74869       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/3/2025 Partial Inspection DANIEL GONZALEZ
Deputy Steel/Welding 9/26/2025 No Access for Inspection DANIEL GONZALEZ
ELECTRICAL-Rough 10/9/2025 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 10/9/2025 Approved DANIEL GONZALEZ
Wood Frame 10/9/2025 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Rough 10/20/2025 Approved DANIEL GONZALEZ
Gas Test 10/20/2025 Approved DANIEL GONZALEZ
Green Building Rough 10/20/2025 Approved DANIEL GONZALEZ
HVAC-Rough 10/20/2025 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 10/21/2025 Approved DANIEL GONZALEZ
Insulation 10/22/2025 Approved DANIEL GONZALEZ
Drywall Nailing 10/27/2025 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 10/27/2025 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready DANIEL GONZALEZ
Service/Power Release 12/29/2025 Approved DANIEL GONZALEZ
Final 1/5/2026 Not Ready for Inspection DANIEL GUEVARA
Footing/Foundation/Slab 1/5/2026 Approved DANIEL GUEVARA
Green Building Final 1/5/2026 Not Ready for Inspection DANIEL GUEVARA
HVAC-Final 1/5/2026 Approved DANIEL GUEVARA
Interior/Exterior Lathing 1/5/2026 Approved DANIEL GUEVARA
PLUMBING-Final 1/5/2026 Approved DANIEL GUEVARA
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved DANIEL GUEVARA
Smoke Detectors 1/5/2026 Approved DANIEL GUEVARA
ELECTRICAL-Final 4/2/2026 Approved DANIEL GUEVARA
Final 4/2/2026 OK to Issue CofO DANIEL GUEVARA
Green Building Final 4/2/2026 Approved DANIEL GUEVARA