16763 W LASSEN ST 91343
Certificate Information: 16763 W LASSEN ST 91343
- Application / Permit
- 24010-20000-04884
- Plan Check / Job No.
- B24VN24054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED 29'-0" x 25'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | ALFRED RAMIREZ |
| Corrections Issued | 12/8/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 12/9/2024 | STEVEN KIM |
| Building Plans Picked Up | 12/26/2024 | APPLICANT |
| Plan Check Approved | 1/14/2025 | ALFRED RAMIREZ |
| Issued | 1/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 12/11/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/12/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 1/14/2025 | ALFRED RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/1/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 4/29/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/19/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 9/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Sewer | 9/24/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 9/24/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 10/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 10/14/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 11/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Insulation | 4/30/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/4/2026 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 6/4/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/4/2026 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 6/4/2026 | Approved | CHRISTOPHER ROJAS |