16763 W LASSEN ST 91343

Certificate Information: 16763 W LASSEN ST 91343

Application / Permit
24010-20000-04884
Plan Check / Job No.
B24VN24054
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED 29'-0" x 25'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
Permit Issued
Issued on 1/16/2025
Issuing Office
Valley
Current Status
Issued on 1/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 ALFRED RAMIREZ
Corrections Issued 12/8/2024 ALFRED RAMIREZ
Quality Review Completed 12/9/2024 STEVEN KIM
Building Plans Picked Up 12/26/2024 APPLICANT
Plan Check Approved 1/14/2025 ALFRED RAMIREZ
Issued 1/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/9/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/9/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/11/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 12/12/2024 CARLOS AGUILERA
Sewer availability Cleared 12/12/2024 CARLOS AGUILERA
GPI Written Notices Cleared 1/14/2025 ALFRED RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/1/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 4/1/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/14/2025 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 4/29/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/19/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 9/24/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/24/2025 Corrections Issued NICHOLAS TROWBRIDGE
Sewer 9/24/2025 Partial Approval NICHOLAS TROWBRIDGE
Underground Mechanical 9/24/2025 Partial Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 10/8/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 10/8/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/8/2025 Approved NICHOLAS TROWBRIDGE
Sewer 10/8/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/14/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 10/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 10/14/2025 Partial Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/12/2025 Partial Approval NICHOLAS TROWBRIDGE
Pre-Inspection 11/12/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Insulation 4/30/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/4/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 6/4/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 6/4/2026 Approved CHRISTOPHER ROJAS
Shower Pan 6/4/2026 Approved CHRISTOPHER ROJAS