13369 W GAGER ST 91331

Certificate Information: 13369 W GAGER ST 91331

Application / Permit
24010-20000-04882
Plan Check / Job No.
B24VN24044
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 1169 SF ADU PER LAMC 12.22 A.33 (c) AND (g), ALL WORK PER ENG DESIGN.
Permit Issued
Issued on 8/20/2025
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/9/2024 LUISANGEL VALENZUELA
Corrections Issued 12/10/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/26/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/7/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/13/2025 LUISANGEL VALENZUELA
Plan Check Approved 8/15/2025 LUISANGEL VALENZUELA
No Progress 8/20/2025 LUISANGEL VALENZUELA
Plan Check Approved 8/20/2025 LUISANGEL VALENZUELA
Issued 8/20/2025 APPLICANT
CofO in Progress 5/22/2026 MICHEL ABAJAN
CofO Issued 6/11/2026 RUBEN SALAS
Permit Finaled 6/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/23/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 4/23/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 6/26/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/26/2025 RYAN CASTRO
Sewer availability Cleared 6/26/2025 RYAN CASTRO
ZI Cleared 6/26/2025 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: NA40169       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/1/2025 Approved MICHEL ABAJAN
Gas Test 12/1/2025 Approved MICHEL ABAJAN
METHANE-Barrier 12/1/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 12/1/2025 Approved MICHEL ABAJAN
Sewer 12/1/2025 Approved MICHEL ABAJAN
Underground Mechanical 12/1/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/11/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 12/11/2025 Partial Approval MICHEL ABAJAN
Insulation 12/12/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/29/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Shower Pan 12/29/2025 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 12/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 1/12/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 1/12/2026 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/20/2026 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/20/2026 Approved MICHEL ABAJAN
HVAC-Rough 1/20/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/20/2026 Approved MICHEL ABAJAN
METHANE-Rough 1/20/2026 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 1/20/2026 Approved MICHEL ABAJAN
Insulation 1/23/2026 Approved MICHEL ABAJAN
Drywall Nailing 1/26/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/2/2026 Approved MICHEL ABAJAN
Final 4/2/2026 Corrections Issued MICHEL ABAJAN
HVAC-Final 4/2/2026 Approved MICHEL ABAJAN
PLUMBING-Final 4/2/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved MICHEL ABAJAN
Service/Power Release 4/2/2026 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/2/2026 Approved MICHEL ABAJAN
Final 5/21/2026 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/21/2026 Approved MICHEL ABAJAN