19258 W STRATHERN ST 91335
Certificate Information: 19258 W STRATHERN ST 91335
- Application / Permit
- 24010-20000-04880
- Plan Check / Job No.
- B24VN24031
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW ONE-STORY DETACHED ACCESSORY DWELLING UNIT AND 2-CAR GARAGE.
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Current Status
- CofO Issued on 12/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2024 | FERNANDO FLORES |
| Corrections Issued | 12/3/2024 | FERNANDO FLORES |
| Plan Check Approved | 1/17/2025 | TSE MING HUANG |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 12/10/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
| CofO Issued | 12/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | KEVIN CHUNG |
| ZA Case | Cleared | 12/30/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 12/31/2024 | KEVIN CHUNG |
Contact Information
| Architect | Cataldo,, John G; Lic. No.: C10457 | 835 MISSION STREET SOUTH PASADENA, CA 91030 |
| Architect | Cataldo,, John G; Lic. No.: NA10457 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Sewer | 3/24/2025 | Approved | JUAN ALVARADO |
| Special/Order Compliance | 3/24/2025 | Corrections Issued | JUAN ALVARADO |
| Underground Mechanical | 3/24/2025 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/15/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 6/17/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 6/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/17/2025 | Approved | JUAN ALVARADO |
| Rough-Elec/Plmb/HVAC | 6/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 6/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/24/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 6/24/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 6/24/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 6/24/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 6/24/2025 | Approved | JUAN ALVARADO |
| Insulation | 6/27/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 6/27/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 7/3/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 7/3/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 7/10/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Grounding or Bonding | 7/10/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/10/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 7/10/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 7/10/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/29/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | JUAN ALVARADO |
| Final | 10/2/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 10/2/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 10/2/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 10/2/2025 | Approved | JUAN ALVARADO |
| Final | 10/7/2025 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 10/7/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 12/3/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Service/Power Release | 12/3/2025 | Approved | ARUTYUN MADATYAN |