6215-6217 N SYLVIA AVE 91335

Certificate Information: 6215-6217 N SYLVIA AVE 91335

Application / Permit
24010-20000-04853
Plan Check / Job No.
B24VN23782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New irregular shaped one story 48' x 52' Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21 with attached ADU per LAMC 12.22 A.33 (c) and (e). NFPA 13D sprinkler required.
Permit Issued
Issued on 1/31/2025
Issuing Office
Current Status
CofO Issued on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 NAREG ATARIAN
Corrections Issued 12/2/2024 NAREG ATARIAN
Quality Review Completed 12/4/2024 OMID HEDAYAT
Building Plans Picked Up 12/4/2024 APPLICANT
Applicant returned to address corrections 1/16/2025 NAREG ATARIAN
Applicant returned to address corrections 1/27/2025 NAREG ATARIAN
Plan Check Approved 1/31/2025 NAREG ATARIAN
Issued 1/31/2025 APPLICANT
CofO in Progress 7/22/2025 SEAN WIRCH
Permit Finaled 9/12/2025 MICHAEL PELHAM
CofO Issued 9/12/2025 MICHAEL PELHAM
Permit Finaled 9/12/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/9/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/9/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/9/2024 RYAN CASTRO
Sewer availability Cleared 12/9/2024 RYAN CASTRO
Hydrant and Access approval Cleared 12/21/2024 LAVEON RIDER
Construction near power lines Cleared 1/10/2025 GEVORK KARAPETYAN
Senate Bill 9 Cleared 1/29/2025 GEORGIA SMITH
ZI Cleared 1/29/2025 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/4/2025 Partial Approval MORRIS JACKSON
Sewer 2/4/2025 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 2/10/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 2/11/2025 Approved MORRIS JACKSON
Special/Order Compliance 2/11/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 3/11/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 3/11/2025 Approved MORRIS JACKSON
Green Building Rough 3/11/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 3/11/2025 Approved MORRIS JACKSON
PLUMBING-Rough 3/11/2025 Corrections Issued MORRIS JACKSON
Verify Sprinkler Sign Off 3/11/2025 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 3/19/2025 Approved MORRIS JACKSON
Green Building Rough 3/19/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/19/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 3/19/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 3/19/2025 Approved MORRIS JACKSON
Insulation 3/25/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/25/2025 Approved MORRIS JACKSON
Shower Pan 3/25/2025 Approved MORRIS JACKSON
Drywall Nailing 4/3/2025 Approved MORRIS JACKSON
Underground Mechanical 5/2/2025 Approved MORRIS JACKSON
Final 6/13/2025 Corrections Issued MORRIS JACKSON
Green Building Final 6/13/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Required MORRIS JACKSON
Service/Power Release 6/13/2025 Not Ready for Inspection MORRIS JACKSON
Smoke Detectors 6/13/2025 Approved MORRIS JACKSON
Final 7/1/2025 Partial Approval MORRIS JACKSON
Service/Power Release 7/1/2025 Approved MORRIS JACKSON