6851 N DE CELIS PL 91406
Certificate Information: 6851 N DE CELIS PL 91406
- Application / Permit
- 24010-20000-04849
- Plan Check / Job No.
- B24VN23763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DETACHED 2-STORY 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT WITH ATTACHED 2-CAR GARAGE, 2ND FLOOR BALCONY AND TRELLIS PER ENGINEERING
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | ALFRED RAMIREZ |
| Corrections Issued | 12/12/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 12/13/2024 | STEVEN KIM |
| Building Plans Picked Up | 12/18/2024 | APPLICANT |
| Applicant returned to address corrections | 3/25/2025 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 4/2/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 4/4/2025 | ALFRED RAMIREZ |
| Issued | 4/8/2025 | APPLICANT |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 12/17/2024 | BRENNEN OBETO |
| Address approval | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/24/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 1/7/2025 | ERNEST TSE |
| Miscellaneous | Cleared | 1/13/2025 | GREGORIO GUILLERMO |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 3/19/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/28/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 5/9/2025 | Approved | SALVADOR MARTINEZ |
| Deputy Wood Construction | 6/2/2025 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 6/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 6/18/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 6/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/7/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/11/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 8/11/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 8/11/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 9/18/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 9/19/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Rough | 9/19/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Rough | 9/19/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 9/23/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 9/23/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 9/23/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 9/29/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 10/3/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 10/3/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/7/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 10/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Drywall Nailing | 10/10/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 10/10/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 3/4/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 3/4/2026 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 3/4/2026 | Corrections Issued | KIRK SANDERS |
| Final | 3/11/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 3/11/2026 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 3/11/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 3/11/2026 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | KIRK SANDERS |
| Final | 3/19/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 3/19/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 3/19/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 3/19/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/21/2026 | Partial Approval | KIRK SANDERS |
| Service/Power Release | 4/21/2026 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 4/29/2026 | No Access for Inspection | MICHAEL CORTEZ |
| Final | 5/26/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 5/26/2026 | Approved | MICHAEL CORTEZ |