9626 N STONEHURST AVE 91352

Certificate Information: 9626 N STONEHURST AVE 91352

Application / Permit
24010-20000-04825
Plan Check / Job No.
B24VN23528
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
CofO Issued on 6/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 KEVIN MORALES
Corrections Issued 12/16/2024 KEVIN MORALES
Quality Review Completed 12/17/2024 EUGENE BARBEAU
Applicant returned to address corrections 7/31/2025 KEVIN MORALES
Plan Check Approved 8/5/2025 KEVIN MORALES
Issued 8/7/2025 APPLICANT
CofO in Progress 5/9/2026 DAVID ANDERSON
Permit Finaled 6/5/2026 RUBEN SALAS
CofO Issued 6/5/2026 RUBEN SALAS
Permit Finaled 6/5/2026 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 1/13/2025 JASON CHAN
Address approval Cleared 1/14/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/14/2025 EDGAR ALCARAZ
Specific Plan Cleared 1/15/2025 DANG NGUYEN
Grading Pre-Inspection Cleared 1/15/2025 CHARLES POWELL
Hydrant and Access approval Cleared 1/23/2025 JERRY KAO
Eng Process Fee Ord 176,300 Cleared 4/22/2025 CARLOS AGUILERA
GPI Written Notices Cleared 7/29/2025 KEVIN MORALES
Private sewage disp. approval Cleared 7/31/2025 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2025 Partial Approval DAVID ANDERSON
Sewer 10/28/2025 Approved DAVID ANDERSON
Special/Order Compliance 10/28/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 11/3/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 11/5/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/26/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/26/2025 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 12/8/2025 Corrections Issued DAVID ANDERSON
Rough-Elec/Plmb/HVAC 12/8/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 12/8/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/23/2025 Partial Approval DAVID ANDERSON
Insulation 12/23/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/23/2025 Partial Approval DAVID ANDERSON
Drywall Nailing 12/30/2025 Approved OGANES TARAKHCHYAN
Shower Pan 1/5/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/8/2026 Approved DAVID ANDERSON
Underground Mechanical 2/27/2026 Partial Approval DAVID ANDERSON
Gas Test 3/20/2026 Approved DAVID ANDERSON
Underground Mechanical 3/20/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 4/27/2026 Approved DAVID ANDERSON
Final 4/27/2026 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Approved DAVID ANDERSON
Service/Power Release 4/27/2026 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 4/27/2026 Approved DAVID ANDERSON
ELECTRICAL-Final 4/30/2026 Approved DAVID ANDERSON
Final 4/30/2026 OK to Issue CofO DAVID ANDERSON
HVAC-Final 4/30/2026 Approved DAVID ANDERSON
PLUMBING-Final 4/30/2026 Approved DAVID ANDERSON
Service/Power Release 4/30/2026 Approved DAVID ANDERSON