8729 N STANSBURY AVE 91402

Certificate Information: 8729 N STANSBURY AVE 91402

Application / Permit
24010-20000-04822
Plan Check / Job No.
B24VN23517
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: PROPOSED 1 STORY 20' X 28' ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 4/3/2025
Issuing Office
Current Status
CofO Issued on 1/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 CRYSTEL MAALOUF
Corrections Issued 12/16/2024 CRYSTEL MAALOUF
Quality Review Completed 12/31/2024 SINA KHOSRAVI
Applicant returned to address corrections 3/27/2025 CRYSTEL MAALOUF
Plan Check Approved 4/3/2025 CRYSTEL MAALOUF
Issued 4/3/2025 APPLICANT
CofO in Progress 12/24/2025 VINCENT HANLEY
Permit Finaled 1/15/2026 RUBEN SALAS
Permit Finaled 1/15/2026 RUBEN SALAS
CofO Issued 1/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/11/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/14/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/16/2025 CARLOS AGUILERA
Sewer availability Cleared 1/16/2025 CARLOS AGUILERA
Construction near power lines Cleared 3/3/2025 GEVORK KARAPETYAN
Construction within easement Cleared 3/3/2025 GEVORK KARAPETYAN

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B       ,
Contractor La Ccs; Lic. No.: 1047699-B       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 1250 W GLENOAKS BLVD E355      GLENDALE, CA 91201

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/10/2025 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 4/15/2025 Corrections Issued MICHEL ABAJAN
Deputy Drilled-In Anchors 4/21/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 4/21/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/21/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/22/2025 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 7/17/2025 Approved KEVIN BERBERYAN
HVAC-Rough 7/17/2025 Approved KEVIN BERBERYAN
Wood Frame 7/17/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 7/21/2025 Partial Approval AMY COLIN
Insulation 7/23/2025 Corrections Issued LOUIS ESCOTO
PLUMBING-Rough 7/23/2025 Approved LOUIS ESCOTO
Drywall Nailing 8/20/2025 Approved DAVID ANDERSON
Insulation 8/20/2025 Approved DAVID ANDERSON
Shower Pan 9/10/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/16/2025 Approved VINCENT HANLEY
Sewer 10/10/2025 Approved VINCENT HANLEY
Underground Mechanical 10/10/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/17/2025 Approved VINCENT HANLEY
Final 12/17/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 12/17/2025 Approved VINCENT HANLEY
Smoke Detectors 12/17/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/17/2025 Not Ready for Inspection VINCENT HANLEY
Final 12/24/2025 OK to Issue CofO VINCENT HANLEY