8729 N STANSBURY AVE 91402
Certificate Information: 8729 N STANSBURY AVE 91402
- Application / Permit
- 24010-20000-04822
- Plan Check / Job No.
- B24VN23517
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: PROPOSED 1 STORY 20' X 28' ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 12/16/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/31/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/27/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/3/2025 | CRYSTEL MAALOUF |
| Issued | 4/3/2025 | APPLICANT |
| CofO in Progress | 12/24/2025 | VINCENT HANLEY |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
| CofO Issued | 1/15/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/16/2025 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/3/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 3/3/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Dhs Ventures Inc; Lic. No.: 1047699-B | , |
| Contractor | La Ccs; Lic. No.: 1047699-B | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 4/15/2025 | Corrections Issued | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/21/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/21/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/22/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/17/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 7/17/2025 | Approved | KEVIN BERBERYAN |
| Wood Frame | 7/17/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/21/2025 | Partial Approval | AMY COLIN |
| Insulation | 7/23/2025 | Corrections Issued | LOUIS ESCOTO |
| PLUMBING-Rough | 7/23/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 8/20/2025 | Approved | DAVID ANDERSON |
| Insulation | 8/20/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 9/10/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/16/2025 | Approved | VINCENT HANLEY |
| Sewer | 10/10/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 10/10/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | VINCENT HANLEY |
| Final | 12/17/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/17/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/17/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 12/17/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 12/24/2025 | OK to Issue CofO | VINCENT HANLEY |