13733 W ARCHWOOD ST 91405

Certificate Information: 13733 W ARCHWOOD ST 91405

Application / Permit
24010-20000-04811
Plan Check / Job No.
B24VN23423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED 2 STORY ACCESSORY DWELLING UNIT (30' X 20') PER LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 2/4/2025
Issuing Office
Valley
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 EDWARD MEHRABIAN
Corrections Issued 12/6/2024 EDWARD MEHRABIAN
Quality Review Completed 12/12/2024 OMID HEDAYAT
Building Plans Picked Up 12/16/2024 APPLICANT
Plan Check Approved 2/4/2025 EDWARD MEHRABIAN
Issued 2/4/2025 APPLICANT
CofO in Progress 7/29/2025 GAREN HAYRAPETYAN
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/18/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/18/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/18/2024 RYAN CASTRO
Sewer availability Cleared 12/18/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 3/25/2025 Partial Approval RYAN SALAZAR
Sewer 3/25/2025 Approved RYAN SALAZAR
Underground Mechanical 3/25/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval RYAN SALAZAR
Insulation 3/27/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 4/3/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval RYAN SALAZAR
Wood Frame 4/3/2025 Partial Inspection RYAN SALAZAR
BUILDING-Rough-Frame 4/29/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/29/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved RYAN SALAZAR
Green Building Rough 4/29/2025 Approved RYAN SALAZAR
HVAC-Rough 4/29/2025 Approved RYAN SALAZAR
PLUMBING-Rough 4/29/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/29/2025 Approved RYAN SALAZAR
Wood Frame 4/29/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/6/2025 Approved RYAN SALAZAR
Shower Pan 5/6/2025 Approved RYAN SALAZAR
Insulation 5/9/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 5/21/2025 Approved RYAN SALAZAR
Insulation 5/21/2025 Approved RYAN SALAZAR
Underground Mechanical 5/21/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 7/22/2025 Corrections Issued GAREN HAYRAPETYAN
Final 7/22/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 7/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Final 7/22/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Final 7/22/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 7/22/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 7/22/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 7/29/2025 Approved GAREN HAYRAPETYAN
Final 7/29/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 7/29/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 7/29/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 7/29/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 7/29/2025 Approved GAREN HAYRAPETYAN