5944-5946 N FULCHER AVE 91601

Certificate Information: 5944-5946 N FULCHER AVE 91601

Application / Permit
24010-20000-04807
Plan Check / Job No.
B24VN23414
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 26'1"X56'5" 1-STORY SINGLE FAMILY DWELLING SB-9 UNIT WITH AN ATTACHED JADU (NFPA 13 D FIRE SPRINKLERS REQUIRED THROUHGOUT) {ALL ELECTRIC BUILDING}
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
Issued on 5/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 MARVEL DELACRUZ
Corrections Issued 12/11/2024 MARVEL DELACRUZ
Quality Review Completed 12/12/2024 JASON HEALEY
Building Plans Picked Up 12/13/2024 APPLICANT
Applicant returned to address corrections 3/26/2025 MARVEL DELACRUZ
Plan Check Approved 5/15/2025 MARVEL DELACRUZ
Issued 5/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/12/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 12/12/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/30/2024 BIAINA HARITUNIAN
Senate Bill 9 Cleared 12/30/2024 ASHLEY RODARTE
Sewer availability Cleared 12/30/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 1/15/2025 PATRICK PEREZ
Construction near power lines Cleared 1/24/2025 GEVORK KARAPETYAN
Construction within easement Cleared 1/24/2025 GEVORK KARAPETYAN
Miscellaneous Cleared 5/9/2025 SUSAN WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/3/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 7/8/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 7/28/2025 No Access for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 7/29/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/31/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Pre-Inspection 8/4/2025 Approved JOSE AVILA
Footing/Foundation/Slab 9/19/2025 Approved JOSE AVILA
Wood Frame 9/19/2025 Corrections Issued JOSE AVILA
Wood Frame 10/17/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 10/28/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval JOSE AVILA
PLUMBING-Rough 11/12/2025 Partial Approval JOSE AVILA
HVAC-Rough 1/13/2026 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/16/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/23/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/13/2026 Corrections Issued MICHAEL CORTEZ
Insulation 2/18/2026 Corrections Issued MICHAEL CORTEZ
Insulation 2/23/2026 Corrections Issued MICHAEL CORTEZ
Insulation 2/25/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/25/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/3/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/9/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/10/2026 Approved GAREN HAYRAPETYAN
Underground Mechanical 4/28/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/1/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/26/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/9/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ