4748 N NOBLE AVE 91403

Certificate Information: 4748 N NOBLE AVE 91403

Application / Permit
24010-20000-04774
Plan Check / Job No.
B24VN23239
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1216 SF SFD EXCEPT FOR 2' OF WALL AND FOUNDATION. REBUILD 63' X 74'-9" IRREGULAR SHAPED 2-STORY SFD W/ 2- CAR GARAGE AND TRELLIS PATIO AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/3/2025
Issuing Office
Current Status
CofO Issued on 12/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 RAPHAEL ROSAS
Corrections Issued 11/26/2024 RAPHAEL ROSAS
Quality Review Completed 12/3/2024 STEVEN KIM
Building Plans Picked Up 12/5/2024 APPLICANT
Applicant returned to address corrections 1/28/2025 RAPHAEL ROSAS
Plan Check Approved 2/3/2025 RAPHAEL ROSAS
Issued 2/3/2025 APPLICANT
CofO in Progress 12/8/2025 JACK KARGODORIAN
Permit Finaled 12/26/2025 RUBEN SALAS
CofO Issued 12/26/2025 RUBEN SALAS
Permit Finaled 12/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/3/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/3/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/3/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 12/9/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/19/2024 BIAINA HARITUNIAN
Trees in Parkway Cleared 12/23/2024 MIGUEL ORNELAS
Permit Cleared 12/30/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/10/2025 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 3/17/2025 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 3/17/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/19/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/19/2025 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval JACK KARGODORIAN
Special/Order Compliance 3/26/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 4/30/2025 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Approved JACK KARGODORIAN
Green Building Rough 4/30/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 4/30/2025 Approved JACK KARGODORIAN
MERV13>=Rough 4/30/2025 Approved JACK KARGODORIAN
Special/Order Compliance 4/30/2025 Corrections Issued JACK KARGODORIAN
Underground Mechanical 4/30/2025 Not Ready for Inspection JACK KARGODORIAN
Deputy Wood Construction 5/1/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/2/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 5/2/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 5/19/2025 Approved JACK KARGODORIAN
Green Building Rough 5/19/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 5/19/2025 Approved JACK KARGODORIAN
Wood Frame 5/19/2025 Approved JACK KARGODORIAN
Shower Pan 5/23/2025 Approved JENNIFER RABUCHIN
Insulation 5/28/2025 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 5/28/2025 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 5/30/2025 Not Ready for Inspection JACK KARGODORIAN
Special/Order Compliance 5/30/2025 Approved JACK KARGODORIAN
Drywall Nailing 6/4/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/4/2025 Approved JACK KARGODORIAN
Final 11/25/2025 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 11/25/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/25/2025 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 11/25/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 11/25/2025 Not Ready for Inspection MISAEL ESPARZA
Final 12/4/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 12/4/2025 Approved JACK KARGODORIAN
Green Building Final 12/4/2025 Approved JACK KARGODORIAN
MERV13>=Final 12/4/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/4/2025 Approved JACK KARGODORIAN
Final 12/5/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 12/5/2025 Approved JACK KARGODORIAN
Special/Order Compliance 12/8/2025 Approved JACK KARGODORIAN