4748 N NOBLE AVE 91403
Certificate Information: 4748 N NOBLE AVE 91403
- Application / Permit
- 24010-20000-04774
- Plan Check / Job No.
- B24VN23239
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 1216 SF SFD EXCEPT FOR 2' OF WALL AND FOUNDATION. REBUILD 63' X 74'-9" IRREGULAR SHAPED 2-STORY SFD W/ 2- CAR GARAGE AND TRELLIS PATIO AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | RAPHAEL ROSAS |
| Corrections Issued | 11/26/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 12/3/2024 | STEVEN KIM |
| Building Plans Picked Up | 12/5/2024 | APPLICANT |
| Applicant returned to address corrections | 1/28/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 2/3/2025 | RAPHAEL ROSAS |
| Issued | 2/3/2025 | APPLICANT |
| CofO in Progress | 12/8/2025 | JACK KARGODORIAN |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/3/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 12/9/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 12/23/2024 | MIGUEL ORNELAS |
| Permit | Cleared | 12/30/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/17/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 3/17/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/19/2025 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | JACK KARGODORIAN |
| Special/Order Compliance | 3/26/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/30/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 4/30/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 4/30/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 4/30/2025 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 4/30/2025 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 4/30/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 5/1/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/2/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/2/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/19/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/19/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 5/19/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 5/23/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/30/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Special/Order Compliance | 5/30/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/4/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/4/2025 | Approved | JACK KARGODORIAN |
| Final | 11/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 11/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 11/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 11/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 12/4/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/4/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 12/4/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 12/4/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 12/4/2025 | Approved | JACK KARGODORIAN |
| Final | 12/5/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 12/5/2025 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 12/8/2025 | Approved | JACK KARGODORIAN |