12064 W NEENACH ST 91352

Certificate Information: 12064 W NEENACH ST 91352

Application / Permit
24010-20000-04770
Plan Check / Job No.
B24VN23237
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW 36' X 27'9" 2 story SB9 unit with attached 1 car garage, NFPA-13D FIRE SPRINKLERS REQUIRED THOUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/23/2025
Issuing Office
Current Status
Issued on 4/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 RARES BODEA
Corrections Issued 12/5/2024 RARES BODEA
Quality Review Completed 12/10/2024 STEVEN KIM
Applicant returned to address corrections 4/8/2025 RARES BODEA
Plan Check Approved 4/11/2025 RARES BODEA
Issued 4/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/17/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/17/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/20/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/20/2024 EDGAR ALCARAZ
Senate Bill 9 Cleared 2/4/2025 DORIAN AGUILAR
Hydrant and Access approval Cleared 3/18/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/12/2025 Partial Inspection MATTHEW NELSON
Pre-Inspection 6/13/2025 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 6/23/2025 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 6/25/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 6/26/2025 Approved MATTHEW NELSON
Underground Mechanical 7/2/2025 Partial Approval MATTHEW NELSON
Wood Frame 7/11/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 8/26/2025 Approved MATTHEW NELSON
HVAC-Rough 8/26/2025 Approved MATTHEW NELSON
PLUMBING-Rough 8/26/2025 Approved MATTHEW NELSON
Underground Mechanical 9/23/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 10/8/2025 Partial Approval MATTHEW NELSON
Insulation 10/21/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/21/2025 Partial Approval MATTHEW NELSON
Drywall Nailing 11/7/2025 Approved MATTHEW NELSON
Green Building Rough 11/7/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/19/2025 Approved CHRISTOPHER MORFIN
BUILDING-Rough-Frame 5/26/2026 Partial Approval MATTHEW NELSON
Final 5/26/2026 Not Ready for Inspection MATTHEW NELSON
Green Building Final 5/26/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 5/26/2026 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 5/26/2026 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 5/26/2026 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 6/24/2026 Approved MATTHEW NELSON
Final 6/24/2026 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 6/24/2026 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 6/24/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/1/2026 SGSOV Not Ready MATTHEW NELSON