8680 N SHARP AVE 91352
Certificate Information: 8680 N SHARP AVE 91352
- Application / Permit
- 24010-20000-04763
- Plan Check / Job No.
- B24VN23189
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY DETACHED 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | ALFRED RAMIREZ |
| Corrections Issued | 11/24/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 11/25/2024 | STEVEN KIM |
| Building Plans Picked Up | 11/26/2024 | APPLICANT |
| Plan Check Approved | 4/8/2025 | ALFRED RAMIREZ |
| Issued | 4/11/2025 | APPLICANT |
| CofO in Progress | 3/9/2026 | MATTHEW NELSON |
| CofO Issued | 4/21/2026 | RUBEN SALAS |
| Permit Finaled | 4/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/11/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/13/2025 | EDGAR ALCARAZ |
| Senate Bill 9 | Cleared | 3/11/2025 | MAYELA VILLA |
| Tract Map conditions | Cleared | 3/11/2025 | MAYELA VILLA |
| ZA Case | Cleared | 3/11/2025 | MAYELA VILLA |
| ZI | Cleared | 3/11/2025 | MAYELA VILLA |
| Hydrant and Access approval | Cleared | 3/20/2025 | FRANK GOMEZ |
| Miscellaneous | Cleared | 4/1/2025 | SIMON LIU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2025 | Corrections Issued | MATTHEW NELSON |
| METHANE-Barrier | 6/3/2025 | Approved | MATTHEW NELSON |
| METHANE-Subgrade | 6/3/2025 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/5/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/20/2025 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 6/20/2025 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 6/25/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/12/2025 | No Access for Inspection | MATTHEW NELSON |
| Green Building Rough | 8/12/2025 | No Access for Inspection | MATTHEW NELSON |
| METHANE-Rough | 8/12/2025 | No Access for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/12/2025 | No Access for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | No Access for Inspection | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 9/9/2025 | Approved | MATTHEW NELSON |
| METHANE-Rough | 9/9/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 9/9/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/29/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/29/2025 | Approved | MATTHEW NELSON |
| Insulation | 9/29/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/29/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 9/29/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/6/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/5/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 11/5/2025 | Approved | MATTHEW NELSON |
| Final | 1/16/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 1/16/2026 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 1/16/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 1/16/2026 | Approved | MATTHEW NELSON |
| Sewer | 2/6/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 2/6/2026 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/12/2026 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/12/2026 | Approved | MATTHEW NELSON |
| Final | 3/6/2026 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 3/6/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 3/6/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Not Required | MATTHEW NELSON |