7331 N WHITE OAK AVE 91335

Certificate Information: 7331 N WHITE OAK AVE 91335

Application / Permit
24010-20000-04728
Plan Check / Job No.
B24VN22883
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-0" X 26'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENG.
Permit Issued
Issued on 12/4/2024
Issuing Office
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2024 APPLICANT
Assigned to Plan Check Engineer 11/20/2024 ARTIN ZARUKIAN
Corrections Issued 11/23/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/26/2024 APPLICANT
Issued 12/4/2024 APPLICANT
CofO in Progress 9/10/2025 ARUTYUN MADATYAN
Permit Finaled 9/26/2025 JOHN JANSON
CofO Issued 9/26/2025 JOHN JANSON
Permit Finaled 9/26/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/25/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/25/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/25/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/27/2024 LEE GUILBEAUX
Sewer availability Cleared 11/27/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2025 Partial Inspection ARUTYUN MADATYAN
PLUMBING-Rough 6/11/2025 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 6/16/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Corrections Issued JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Approved JUAN ALVARADO
Underground Mechanical 7/9/2025 Approved JUAN ALVARADO
Rough-Elec/Plmb/HVAC 7/10/2025 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 7/15/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/18/2025 Approved JUAN ALVARADO
Green Building Rough 7/18/2025 Approved JUAN ALVARADO
Verify Sprinkler Sign Off 7/18/2025 Approved JUAN ALVARADO
Insulation 7/24/2025 Approved JUAN ALVARADO
Drywall Nailing 7/28/2025 Not Ready for Inspection JUAN ALVARADO
Shower Pan 7/28/2025 Approved JUAN ALVARADO
Drywall Nailing 7/30/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 7/30/2025 Partial Approval GEVORK IPCHYAN
Service/Power Release 8/21/2025 Partial Inspection JUAN ALVARADO
Service/Power Release 9/4/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Final 9/8/2025 Approved ARUTYUN MADATYAN
Final 9/8/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 9/8/2025 Approved ARUTYUN MADATYAN
HVAC-Final 9/8/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 9/8/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 9/8/2025 Approved ARUTYUN MADATYAN
Smoke Detectors 9/8/2025 Approved ARUTYUN MADATYAN