6256 N SATSUMA AVE 91606

Certificate Information: 6256 N SATSUMA AVE 91606

Application / Permit
24010-20000-04727
Plan Check / Job No.
B24VN22879
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN PROPOSED 1 STORY SB9 DWELLING PER WFPP **13D SPRINKLER REQUIRED**
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
Issued on 3/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/13/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 KHUONG TRUONG
Corrections Issued 12/3/2024 KHUONG TRUONG
Quality Review Completed 12/10/2024 PRANITA SHAH
Applicant returned to address corrections 12/31/2024 KHUONG TRUONG
Plan Check Approved 3/10/2025 KHUONG TRUONG
Issued 3/12/2025 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/20/2024 RICARDO BOHORQUEZ
Address approval Cleared 12/24/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 12/24/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/26/2024 RYAN CASTRO
Sewer availability Cleared 12/26/2024 RYAN CASTRO
Senate Bill 9 Cleared 12/27/2024 BRENNEN OBETO
Hydrant and Access approval Cleared 3/6/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/16/2025 No Access for Inspection JOSE AVILA
PLUMBING-Rough 4/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 4/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 5/9/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 5/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/12/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 10/3/2025 Approved JOSE AVILA
ELECTRICAL-Rough 10/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/14/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/14/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/20/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/20/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/20/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 10/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 11/3/2025 Not Ready for Inspection JOSE AVILA
Underground Mechanical 11/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 12/22/2025 Partial Approval JOSE AVILA
Drywall Nailing 12/26/2025 Approved CHRISTOPHER MORFIN
Final 1/12/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 1/12/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Final 2/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/24/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/24/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/24/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/9/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 6/9/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Posting Pre-Inspection 6/9/2026 Partial Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 6/9/2026 SGSOV No Gas GAREN HAYRAPETYAN
Service/Power Release 6/9/2026 Conditional Approval GAREN HAYRAPETYAN
Smoke Detectors 6/9/2026 Approved GAREN HAYRAPETYAN
Verify Rec and Parks Fee Memo 6/9/2026 Not Ready for Inspection GAREN HAYRAPETYAN