12952 W HUSTON ST 91423
Certificate Information: 12952 W HUSTON ST 91423
- Application / Permit
- 24010-20000-04718
- Plan Check / Job No.
- B24VN22815
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 66'-1" X 51'-6" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | SELLA BENYAMIN |
| Corrections Issued | 11/21/2024 | SELLA BENYAMIN |
| Quality Review Completed | 11/21/2024 | STEVEN KIM |
| Building Plans Picked Up | 11/21/2024 | APPLICANT |
| Plan Check Approved | 12/12/2024 | SELLA BENYAMIN |
| Plan Check Approved | 12/12/2024 | SELLA BENYAMIN |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 12/23/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
| CofO Issued | 1/8/2026 | RUBEN SALAS |
| Permit Finaled | 1/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/22/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 12/3/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/8/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Special/Order Compliance | 1/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 1/23/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 2/19/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 2/27/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/23/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/23/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/23/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/8/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/8/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/19/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/24/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 9/24/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 12/17/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 12/22/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 12/22/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/22/2025 | Approved | OGANES TARAKHCHYAN |