7247 N CLEON AVE 91352

Certificate Information: 7247 N CLEON AVE 91352

Application / Permit
24010-20000-04713
Plan Check / Job No.
B24VN22782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) 2-STORY ADU. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 3/19/2025
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 ADRIANA LOPEZ
Corrections Issued 11/30/2024 ADRIANA LOPEZ
Quality Review Completed 12/9/2024 PRANITA SHAH
Applicant returned to address corrections 2/12/2025 ADRIANA LOPEZ
Plan Check Approved 3/17/2025 ADRIANA LOPEZ
Issued 3/19/2025 APPLICANT
CofO in Progress 2/24/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 3/13/2026 RUBEN SALAS
CofO Issued 3/13/2026 RUBEN SALAS
Permit Finaled 3/13/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/9/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 12/9/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/11/2024 CARLOS RAMIREZ
Sewer availability Cleared 12/11/2024 CARLOS RAMIREZ
Permit Cleared 1/7/2025 LEE GUILBEAUX
Trees in Parkway Cleared 1/7/2025 MIGUEL ORNELAS
Public Works-Highway Ded. Cleared 1/7/2025 LEE GUILBEAUX
Construction near power lines Cleared 1/22/2025 GEVORK KARAPETYAN
Construction within easement Cleared 1/22/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/17/2025 No Access for Inspection JOSE AVILA
Underground Mechanical 4/17/2025 No Access for Inspection JOSE AVILA
PLUMBING-Rough 4/28/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/13/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 8/18/2025 No Access for Inspection JOSE AVILA
Pre-Inspection 8/20/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 8/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 9/8/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 9/18/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 10/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/22/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/22/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 11/6/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/13/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 11/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 11/13/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 2/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/17/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/23/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Gas Test 2/23/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/23/2026 Approved ROBERTO PALACIOS-LOPEZ