7247 N CLEON AVE 91352
Certificate Information: 7247 N CLEON AVE 91352
- Application / Permit
- 24010-20000-04713
- Plan Check / Job No.
- B24VN22782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan (N) 2-STORY ADU. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | ADRIANA LOPEZ |
| Corrections Issued | 11/30/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 12/9/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 2/12/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 3/17/2025 | ADRIANA LOPEZ |
| Issued | 3/19/2025 | APPLICANT |
| CofO in Progress | 2/24/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 12/11/2024 | CARLOS RAMIREZ |
| Permit | Cleared | 1/7/2025 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 1/7/2025 | MIGUEL ORNELAS |
| Public Works-Highway Ded. | Cleared | 1/7/2025 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/22/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/22/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/17/2025 | No Access for Inspection | JOSE AVILA |
| Underground Mechanical | 4/17/2025 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/13/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 7/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/18/2025 | No Access for Inspection | JOSE AVILA |
| Pre-Inspection | 8/20/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 10/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/22/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 10/22/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 10/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 11/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 11/13/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 11/18/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/17/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/17/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/23/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 2/23/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/23/2026 | Approved | ROBERTO PALACIOS-LOPEZ |