949 S MALCOLM AVE 90024

Certificate Information: 949 S MALCOLM AVE 90024

Application / Permit
24010-20000-04707
Plan Check / Job No.
B24VN22692
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 13'-9" X 13'-9" DETACHED PATIO COVER PER ENGINEERING.
Permit Issued
Issued on 1/28/2025
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/20/2024 ARTIN ZARUKIAN
Corrections Issued 11/25/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/26/2024 APPLICANT
Plan Check Approved 1/28/2025 ALEC MOUSAKHANIAN
Issued 1/28/2025 APPLICANT
CofO in Progress 5/14/2025 MICHAEL PELHAM
Permit Finaled 5/15/2025 RICHARD STEINBACH
CofO Issued 5/15/2025 RICHARD STEINBACH
Permit Finaled 5/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/2/2024 VASIL MIHALEV
Specific Plan Cleared 1/8/2025 PEDRO AYALA
Roof/Waste drainage to street Cleared 1/10/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/15/2025 EDGAR ALCARAZ
Miscellaneous Cleared 1/24/2025 HISASHI KOBAYAKAWA

Contact Information

Contractor Precise Home Builders Inc; Lic. No.: 515469-B 15125 VENTURA BLVD #201      SHERMAN OAKS, CA 91403
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 3/11/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Approved DANIEL VERA
Verify Sprinkler Sign Off 3/11/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 3/24/2025 Approved DANIEL VERA
Interior/Exterior Lathing 3/24/2025 Approved DANIEL VERA
Drywall Nailing 5/7/2025 Approved DANIEL VERA
Final 5/7/2025 Corrections Issued DANIEL VERA
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved DANIEL VERA
Service/Power Release 5/7/2025 Approved DANIEL VERA
Final 5/13/2025 OK to Issue CofO DANIEL VERA