Excavation/Setback/Form/Re-Bar
|
3/19/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Pre-Inspection
|
3/19/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
PLUMBING-Rough
|
3/24/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
Underground Mechanical
|
3/24/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2025
|
Approved
|
MATTHEW NELSON
|
|
FLOOD-Elevation Certificate
|
4/1/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Footing/Foundation/Slab
|
4/1/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
Reinforced Concrete Frame
|
4/1/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Reinforced Masonry Frame
|
4/1/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
BUILDING-Rough-Frame
|
4/16/2025
|
Not Ready for Inspection
|
DAVID MATSON
|
|
FLOOD-Proofing Certificate
|
4/16/2025
|
Corrections Issued
|
DAVID MATSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2025
|
Partial Approval
|
DAVID MATSON
|
|
Green Building Rough
|
4/16/2025
|
Not Ready for Inspection
|
DAVID MATSON
|
|
Verify Sprinkler Sign Off
|
4/16/2025
|
Not Ready for Inspection
|
DAVID MATSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/23/2025
|
Corrections Issued
|
NICHOLAS TROWBRIDGE
|
|
BUILDING-Rough-Frame
|
5/7/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
Deputy Wood Construction
|
5/7/2025
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Drywall Nailing
|
5/7/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
FLOOD-Proofing Certificate
|
5/7/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
Green Building Rough
|
5/7/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
HVAC-Rough
|
5/7/2025
|
Corrections Issued
|
NICHOLAS TROWBRIDGE
|
|
PLUMBING-Rough
|
5/7/2025
|
Corrections Issued
|
NICHOLAS TROWBRIDGE
|
|
Verify Sprinkler Sign Off
|
5/7/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
Wood Frame
|
5/7/2025
|
Corrections Issued
|
NICHOLAS TROWBRIDGE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/9/2025
|
No Access for Inspection
|
NICHOLAS TROWBRIDGE
|
|
BUILDING-Rough-Frame
|
5/14/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
ELECTRICAL-Rough
|
5/14/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
FLOOD-Proofing Certificate
|
5/14/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2025
|
Partial Approval
|
NICHOLAS TROWBRIDGE
|
|
Green Building Rough
|
5/14/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
PLUMBING-Rough
|
5/14/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
Wood Frame
|
5/14/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
BUILDING-Rough-Frame
|
5/28/2025
|
Partial Approval
|
NICHOLAS TROWBRIDGE
|
|
FLOOD-Proofing Certificate
|
5/28/2025
|
Corrections Issued
|
NICHOLAS TROWBRIDGE
|
|
HVAC-Final
|
5/28/2025
|
Not Ready for Inspection
|
NICHOLAS TROWBRIDGE
|
|
HVAC-Rough
|
5/28/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
Interior/Exterior Lathing
|
5/28/2025
|
Partial Approval
|
NICHOLAS TROWBRIDGE
|
|
Wood Frame
|
5/28/2025
|
Approved
|
NICHOLAS TROWBRIDGE
|
|
Insulation
|
6/4/2025
|
Approved
|
MATTHEW NELSON
|
|
PLUMBING-Rough
|
6/12/2025
|
Approved
|
MATTHEW NELSON
|
|
Sewer
|
6/12/2025
|
Approved
|
MATTHEW NELSON
|
|
Drywall Nailing
|
6/13/2025
|
Approved
|
MATTHEW NELSON
|
|
Interior/Exterior Lathing
|
6/13/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Interior/Exterior Lathing
|
6/27/2025
|
Approved
|
MATTHEW NELSON
|
|
Shower Pan
|
6/27/2025
|
Approved
|
MATTHEW NELSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/10/2025
|
Conditional Approval
|
DAVID MATSON
|
|
PLUMBING-Rough
|
7/10/2025
|
Approved
|
DAVID MATSON
|
|
Underground Mechanical
|
7/10/2025
|
Partial Approval
|
DAVID MATSON
|
|
Gas Test
|
8/26/2025
|
Approved
|
MATTHEW NELSON
|
|
PLUMBING-Final
|
8/26/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
PLUMBING-Rough
|
8/26/2025
|
Approved
|
MATTHEW NELSON
|
|
BUILDING-Rough-Frame
|
9/11/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
FLOOD-Elevation Certificate
|
9/11/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
FLOOD-Proofing Certificate
|
9/11/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Final
|
9/11/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Footing/Foundation/Slab
|
9/11/2025
|
Partial Approval
|
MATTHEW NELSON
|
|
Green Building Final
|
9/11/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
SGSOV-Seismic Gas S/O Valve
|
9/11/2025
|
SGSOV Approved
|
MATTHEW NELSON
|
|
Service/Power Release
|
9/11/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Smoke Detectors
|
9/11/2025
|
Approved
|
MATTHEW NELSON
|
|
BUILDING-Rough-Frame
|
9/24/2025
|
Approved
|
MATTHEW NELSON
|
|
ELECTRICAL-Final
|
9/24/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
FLOOD-Elevation Certificate
|
9/24/2025
|
Approved
|
MATTHEW NELSON
|
|
FLOOD-Proofing Certificate
|
9/24/2025
|
Approved
|
MATTHEW NELSON
|
|
Final
|
9/24/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Footing/Foundation/Slab
|
9/24/2025
|
Approved
|
MATTHEW NELSON
|
|
Green Building Final
|
9/24/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Service/Power Release
|
9/24/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Final
|
10/29/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Green Building Final
|
10/29/2025
|
Corrections Issued
|
MATTHEW NELSON
|
|
Service/Power Release
|
10/29/2025
|
Not Ready for Inspection
|
MATTHEW NELSON
|
|
Final
|
11/17/2025
|
OK to Issue CofO
|
MATTHEW NELSON
|
|
Green Building Final
|
11/17/2025
|
Approved
|
MATTHEW NELSON
|
|
Service/Power Release
|
11/17/2025
|
Approved
|
MATTHEW NELSON
|