1124-1124 1/2 E 45TH ST 90011

Certificate Information: 1124-1124 1/2 E 45TH ST 90011

Application / Permit
24010-20000-04684
Plan Check / Job No.
B24VN22626
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan ***PROPOSED 2 ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/9/2025
Issuing Office
Current Status
CofO Issued on 4/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 SINA KHOSRAVI
Corrections Issued 11/26/2024 SINA KHOSRAVI
Quality Review Completed 12/6/2024 GARO TELMI
Applicant returned to address corrections 1/14/2025 SINA KHOSRAVI
Plan Check Approved 2/4/2025 SINA KHOSRAVI
Issued 2/9/2025 APPLICANT
CofO in Progress 4/23/2026 ALEJANDRO DE ARTOLA
Permit Finaled 4/26/2026 DEROLD HAUFF
Permit Finaled 4/26/2026 DEROLD HAUFF
CofO Issued 4/26/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 12/10/2024 RUBEN VASQUEZ
Tenant Habitability Plan Cleared 12/11/2024 KORNEL LELEA
Address approval Cleared 12/19/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 12/19/2024 ADRIAN SANCHEZ
Sewer availability Cleared 12/19/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 12/26/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Kamboj,, Naresh Chande; Lic. No.: C21893 7838 QUIMBY AVE      CANOGA PARK, CA 91304
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/13/2025 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 6/20/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/20/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/22/2025 Approved ALEJANDRO DE ARTOLA
Sewer 7/22/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/22/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/15/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 10/1/2025 Approved LUIS CASTRO
HVAC-Rough 10/1/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 10/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 10/3/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/3/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 10/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/8/2025 Approved ALEJANDRO DE ARTOLA
Insulation 10/8/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/9/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/9/2025 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/10/2025 Approved ALEX COLIN
ELECTRICAL-Final 2/18/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/18/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/18/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/4/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/4/2026 Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/4/2026 Approved ALEJANDRO DE ARTOLA
Final 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/1/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 4/1/2026 Approved ALEJANDRO DE ARTOLA
Final 4/23/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 4/23/2026 Approved ALEJANDRO DE ARTOLA