13029 N BORDEN AVE 91342
Certificate Information: 13029 N BORDEN AVE 91342
- Application / Permit
- 24010-20000-04645
- Plan Check / Job No.
- B24VN22345
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: new Accessory dwelling unit per LAMC 12.22 A.33(c) and (e), all work per wfpp
- Permit Issued
- Issued on 12/14/2024
- Issuing Office
- Current Status
- CofO Issued on 10/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/14/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 11/27/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/12/2024 | MOHAMMAD ESMAILI |
| Issued | 12/14/2024 | APPLICANT |
| CofO in Progress | 10/17/2025 | KEVIN BERBERYAN |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
| CofO Issued | 10/24/2025 | RUBEN SALAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/18/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/14/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/23/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 4/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/16/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 4/21/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 4/21/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/21/2025 | Partial Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/1/2025 | Approved | LOUIS ESCOTO |
| Insulation | 5/15/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/15/2025 | Corrections Issued | KEVIN BERBERYAN |
| Shower Pan | 5/15/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/21/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 10/8/2025 | Approved | KEVIN BERBERYAN |
| Final | 10/8/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 10/8/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/8/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 10/8/2025 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 10/8/2025 | Approved | KEVIN BERBERYAN |