7408 N SATSUMA AVE 91352
Certificate Information: 7408 N SATSUMA AVE 91352
- Application / Permit
- 24010-20000-04641
- Plan Check / Job No.
- B24VN22322
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-0" X 27'-6" DETACHED ACCESSORY DWELLING UNIT W/ 5'-5" X 3'-6" PORCH PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 11/16/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/18/2024 | APPLICANT |
| Plan Check Approved | 1/17/2025 | ISIS ARGUETA |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 11/3/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
| CofO Issued | 11/19/2025 | RUBEN SALAS |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/20/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/10/2025 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/8/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/8/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 5/8/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 5/8/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/8/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/8/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/20/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 6/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 6/30/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/2/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/2/2025 | Approved | MICHAEL CORTEZ |
| Final | 9/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 9/25/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |