7408 N SATSUMA AVE 91352

Certificate Information: 7408 N SATSUMA AVE 91352

Application / Permit
24010-20000-04641
Plan Check / Job No.
B24VN22322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-0" X 27'-6" DETACHED ACCESSORY DWELLING UNIT W/ 5'-5" X 3'-6" PORCH PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 ARTIN ZARUKIAN
Corrections Issued 11/16/2024 ARTIN ZARUKIAN
Building Plans Picked Up 11/18/2024 APPLICANT
Plan Check Approved 1/17/2025 ISIS ARGUETA
Issued 1/17/2025 APPLICANT
CofO in Progress 11/3/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/19/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/20/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/20/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/10/2025 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 3/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/8/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/8/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/8/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval JOSE AVILA
HVAC-Rough 5/8/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/8/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/8/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Sewer 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/20/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 6/30/2025 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 7/2/2025 Approved MICHAEL CORTEZ
Shower Pan 7/2/2025 Approved MICHAEL CORTEZ
Final 9/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/5/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/25/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/25/2025 Approved ROBERTO PALACIOS-LOPEZ